Metro Reports: Adidas Campus Expansion, Robert & Ann Sacks House, 7 Southeast Stark, and more

7 Southeast Stark

A building permit was issued for Harsch Investment Properties’ 7 Southeast Stark development, designed by Works Progress Architecture

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers December 4th to December 10th, 2017.

Early Assistance has been requested by Barghausen Consulting Engineers Inc for a project at 8123 SE 17th Ave:

Future code – Construction of a 13,292 square foot retail pharmacy with parking for 20 vehicles.

Early Assistance has been requested for a project at 7119 SE Knight St:

Current Code – Proposal is for a Type 2 Conditional Use review to remove properties from the boundary (approved through LUR 96-00181 CU) for a future multi-dwelling development.

Early Assistance has been requested for the Adidas Campus Expansion at 5060 N Greeley Ave:

Future code: Proposal is for a new office building, new amenity building, new underground parking garage, right-of-way work; new site work and landscape at existing campus.

Early Assistance has been requested by Baysinger Partners for a project at SE 24th & Tacoma:

Current code: Construction of two (2) commercial pad buildings, one with drive-through, 33 vehicular parking stalls, landscaping, and ped walkways/plazas and two (2) accesses to SE Tacoma St. One access is full ingress/egress, the second is drive-through egress only.

A Pre-Application Conference has been scheduled to discuss a project at 1512 SW 58th Ave:

Site zone will change to R2 under new code. 11 new condos, both existing homes to remain. PLA adjustment may be submitted to separate existing homes from remainder of the site. There is no Type III but applicant still wants to do this as a PC.

A building permit was issued to Allied Works Architecture for the rebuild of the Robert and Ann Sacks House at 2281 NW Glisan St:

Repair to 5-story building damaged by explosion – repair damaged structural members, terrace, & roof; install new MEP systems, exterior cladding, elevator, interior walls, fixtures, & finishes; no change to footprint *** mech separate ***

A building permit was issued to Siteworks Design | Build for the final building of the Sunshine Portland development at 3680 SE 29th Ave:

New 15 unit four story apartment building. ( building 4 of complex) with associated site work

A building permit was issued to Works Progress Architecture for 7 Southeast Stark:

New core and shell development of 5 story CIP concrete slabs and columns, 5 story steel frame with composite steel floor decks, mixed-use with ground floor industrial service, 6 floors of commercial parking and 4 floors of industrial and traditional office.

Metro Reports: Division 33, Convention Center Hotel, New Omni, and more

The Theory 33 Flats will include 30 residential units over ground floor retail.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. (Note: this post covers August 7th to 13th, 2017; last week’s intakes will be covered in a subsequent post.)

Early Assistance has been requested for a project at 1602 SE Tacoma St:

Proposal is to construct a twelve unit apartment building with one and two bedroom units alongside a pedestrian passageway and a central stair to the upper units. Concept development from building at 686 SE Spokane St. The existing structure will be deconstructed by a certified deconstruction contractor. The applicant wishes to use Community Design Standards and wishes to confirm that a Type II Design Review will not be required. Applicant will use current zoning code for review.

Early Assistance has been requested by DiLoreto Architecture for a project at 6615 SE 52nd Ave:

Current code. 32 unit housing constructed within an existing office building. no additional square footage proposed. Existing parking and site to remain.

Early Assistance has been requested by MWA Architects for a project at 9747 NE Glisan St:

Project is intended as affordable workforce multi-family residential development. This project includes 3,500 square feet of resident service/community space and 164 apartment units.

Early Assistance has been requested by Winn Architecture for a project at 3336 SW 11th Ave:

Proposal is for a 18 unit, three story with basement apartment building with ground floor commercial space.

A Pre-Application Conference has been scheduled by Ankrom Moisan Architects to the discuss the New Omni at 416 NW 5th Ave:

Current code. Request for a Pre-App for a Type IV and Type III land use review for one contributing structure (416 NW 5th) and non-contributing structure (430 NW 5th Ave) for a proposal of a new 14 story, 150,000 GSF mixed use residential development with parking. Stormwater disposal via landscaped planter.

The PCC Child Development Center at 11900 SW 49th Ave has been submitted for building permit review by GBD Architects:

Addition of new 2-story building for classroom and office space; mixed occupancy B and E; new covered walkway to connect 2 existing buildings with new; TI in ground floor of existing buildings change of occupancy from B to E, replace exterior windows and new walls to reconfigure classrooms; and all associated site work

A fourth building at the Sunshine Portland development, located at 3610 SE 29th Ave, has been submitted for building permit review by Siteworks Design Build:

New 15 unit four story apartment building. ( building 4 of complex) with associated site work

525 SE MLK Blvd has been submitted for building permit review by Hacker Architects:

New construction of six story (above ground) building consisting of 90,400 SF with one level of underground parking consisting of 15,490 SF; five levels of office over ground floor retail

A building permit was issued to Hacker Architects for the Theory 33 Flats at 3325 SE Division St:

Construct new 4 story, 30 unit apartment building, trash area at main floor of building, includes associated site work

A building permit was issued to Carleton Hart Architecture for New Meadows at 4353 N Hunt St (previously 8710 N Dana Ave):

New 15 unit 2 story housing facility for youth transitioning out of foster care

A building permit was issued to Deca, Inc for a project at 1728 NE 45th Ave:

New 3 story w/ basement, 12 unit apartment building , includes associated sitework – prelim mtg 16-289387 BD ***separate mechanical permit required***

A building permit was issued for a project at 85 N Going St (previously 25 N Going St):

New 3 story 6 plex and associated site work; approx 75 sq ft trash enclosure

The first building permit was issued for the Convention Center Hotel at 375 NE Holladay St:

Excavation and shoring, underground utilities, stuctural foundations, vertical structure only, vertical fire protection standpipe at stairs

Metro Reports: The Dianne, 2731 SE Belmont St, 3610 SE 29th Ave and more

The Diane

A Building Permit was issued for The Dianne apartments at NW 11th & Hoyt

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits. We publish the highlights.

Early Assistance has been requested for a project at 6702 SE 72nd Ave:

Proposal is for a 14 unit multi-family buildings: (2) six plex and (1) duplex. On-site parking is proposed.

Early Assistance has been requested by TVA Architects for a project at 4946 NE 13th Ave:

Proposal for a 4-story mixed use multi-family apartment project with ground floor retail. No parking provided.

A Pre-Application Conference has been scheduled by Holst Architecture to discuss a project at 1135 SE Grand Ave: 

Pre-app conference for a Type III review of proposal to demo existing bldg and replace with new construction of 14,780 sf mixed occupancy two story structure.

Three buildings at 3610 SE 29th Ave have been submitted for building permit review by Siteworks Design Build:

New construction- 4/story multifamily apartment building (building 1 of 3), new access drive, 51 parking spaces, pedestrian site circulation, landscape areas and storwater facilites

New construction- 4/story multifamily apartment building (building2 of 3),

New construction- 4/story multifamily apartment building (building 3 of 3),

A project at 2023 NE 42nd Ave has been submitted for building permit review by Urban Development Group:

Construct new 5 story mixed use building; main floor to include 2 residential units, bike storage, and commercial space for future tenant; 2nd thru 5th fl to include 30

A project at 15023 SE Stark St has been submitted for building permit review by DECA Architecture:

New 3 story 40 unit apartment building, site improvements, stormwater facility, and 21 stall parking lot.

A project at 2731 SE Belmont St has been submitted for building permit review:

Construct new 5 story (46) apartment building with associated site work

A project at 2031 SW 10th Ave has been submitted for building permit review by SERA Architects:

New 5 story wood framed apartment building above one level of below grade parking

A project at 533 NE Killingsworth St has been submitted for building permit review by Design Department Architecture:

Construction of new single commercial building for use as restaurant to include dining area, kitchen, storage, (2) bathrooms, offices, and walk in cooler; outdoor patio; onsite stormwater and landscaping as required

A building permit was issued for a project at 1650 SE Tacoma St (formerly 1640 SE Tacoma St):

New 5 story apartment building with 44 units and green roof. Ground floor contains (1) retail space and parking garage. No occupancy for retail space on this permit, interior trash area at parking garage level

A building permit was issued to Ankrom Moisan Architects for The Dianne at 535 NW 11th Ave:

New 14-story, 102 unit residential building with 2 ground floor retail spaces. 50 mechanical parking spaces plus 2 ADA parking spaces.

Metro Reports: Hotel Cornelius, PSU Viking Pavilion, 2100 SE Belmont St and more

Conceptual image of PSU Viking Pavilion

Conceptual image of PSU Viking Pavilion

Every week, the Bureau of Development Services publishes lists of early assistance applications, land use reviews and building permits. We publish the highlights.

Merryman Barnes Architects and Encore Architects have requested Design Advice for a project at 1400 NW Raleigh St:

Six story multi plex- 145 units, residential, with below grade parking

Early Assistance has been requested by Woofter Architecture for the PSU Viking Pavilion:

Modernization & upgrade of existing Peter Scott [sic] Center. Additional classrooms & the addition of a multi purpose arena (viking pavillion)

Early Assistance has been requested by Siteworks Design | Build for a project at 3610 SE 29th Ave:

Phase 1 of new multi family dwelling structures. 62 dwelling units total. 1 3-story structure on R1 parcel, 2 4-story structures on CG parcel. Ground floor residential with parking and landscaping. Phase 2 will be new 4-story hostel with 25 dwelling units.

MCA Architects have applied for a Type III Historic Resource Review for the renovation of the Woodlark Building and Hotel Cornelius:

Renovate and restore the two historic buildings for reuse

A building permit is under review for a new building at 2100 SE Belmont St by Urban Development Group:

Construct new 4 story 55 unit apartment building with underground parking; associated site work

A buiding permit has been issued for a new building at 7617 NE Sandy Blvd:

Construct new one story building with associated site work