Metro Reports: Mt. Scott Community Center Seismic Retrofit and Expansion Project, Albina & Prescott Apartments, 4520 N Colonial, and more

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers October 11th, 2021 to October 17th, 2021.

Early Assistance has been requested by FFA Architecture & Interiors for the Mt. Scott Community Center Seismic Retrofit and Expansion Project at 5516 SE 72nd Ave:

Demolition of ~18,000 sf of existing structure, renovation of ~35,000 sf of existing structure and ~30,000 sf 2-story addition. Site work as required to bring non-conforming situations into compliance
with Title 33.

A project at 4520 N Colonial Ave has been submitted for building permit review by Works Progress Architecture:

4520 N COLONIAL – New three story, 18 unit apartment building with support spaces and amenities including exterior patios and common areas; includes site work *** w/21-
087312-CO and 21-087305-MT ***

A project at 1560 N Going Ave has been submitted for building permit review by Works Progress Architecture:

1560 N GOING – New three story, 32 unit apartment building with support spaces and amenities including exterior patios and common areas; includes site work and designated
access for fire and pedestrians by easements through the adjacent site. *** w/21-087269-MT ***

The Albina & Prescott Apartments at 751 N Prescott St have been submitted for building permit review:

Construct a new 4-story, 29 unit, wood framed multi family building with support spaces. (w/ 21-087218-MT)

Metro Reports: Adidas Campus Expansion, Tree Farm, 555 SE MLK, and more

Image of one of the three new buildings by Lever Architecture’s proposed at the Adidas Campus, as seen from the corner of N Sumner and Delaware.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers June 18th to June 24th, 2018. 

Design Advice has been requested by Holst Architecture for a project at 2310 N Hunt St:

DESIGN HEARING – Design Advice Request for 42 dwelling units in four building with surface parking and associated site landscape elements. Stormwater will be managed on site.

Early Assistance has been requested for a project at 2628 SE Belmont St:

Demolish existing building and construct a new 4-story, 44-unit, apartment building with retail on the first floor.

A Pre-Application Conference has been scheduled by BBL Architects to a discuss a project at 725 NE 100th Ave:

Pre-application conference for a proposed elementary school in David Douglas school district.

A Pre-Application Conference has been scheduled by Works Progress Architecture to a discuss a project at 1431 N Church St:

Proposed new mixed use apartment complex approx 90,000 GSF with six levels of apartments above one level of retail and building amenity space.

The Adidas Campus Expansion was submitted for Type II Design Review by Lever Architecture:

Proposal is for three new buildings, site work, right of way work, renovation to existing plaza, new landscaping and relocation of the Adidas Village arrival drive to create a cohesive intersection at N. Greeley Ave.

A project at 203 NE Grand Ave was submitted for Type III Design Review by Ankrom Moisan Architects:

New construction of an eight story mixed use building with one level of underground parking. Approximately 170 apartments on levels 2-8, 5,500 SF of retail on ground floor. Amenities include a lounge, fitness, leasing, bike storage, pet area and wash.

A project at 6123 N Lombard St was submitted for building permit review by FFA Architecture & Interiors:

New 4 story mixed use apartment building with 46 living units and retail space and garage parking

A building permit was issued for a project at 1415 SE Pardee St (formerly 4540 SE Milwaukie Ave):

Construction of new 4 story apartment building (44 units); garage on first floor;

Building permits were issued for a project at 3445 SE Gladstone St:

Bldg A – 1 of 3 new buildings w/ (E) building to remain, all on same lot – 2 story- with basement – 7 unit apartment building w/ onsite parking, includes associated sitework *** w/ detached trash enclosure 17-248414-CO & 17-248408-MT***

Bldg B – 2 of 3 new buildings w/ (E) building to remain, all on same lot – 2 story with basement , 8 unit apartment building *** w/ 17-248411-MT ***

A building permit was issued to Hacker Architects for a project at 555 SE Martin Luther King Jr Blvd:

New construction of six(story (above ground) building consisting of 90,400 SF with one level of underground parking consisting of 15,490 SF; five levels of office over ground floor retail , CLT floor system.

A building permit was issued for Tree Farm at 826 SE 3rd Ave:

New 6-story commercial building; 1st floor future retail tenant, lobby and trash room; floors 2-6 F2 occupancy; and associated site work, no occupancy this permit *** mechanical permit 17-196436 MT***

Metro Reports: Four+Montgomery, SW 3rd & Ash, St John Fisher Parish, and more

The PSU Four+Montgomery project, as shown to the Design Commission

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers April 9th to April 15th, 2018. 

Design Advice has been requested by SERA Architects for a project at 1715 SW Salmon St:

7-story mixed use building (177 units) with 8,800 square feet of retail space on the ground floor. Twenty-seven parking spaces are proposed with access from SW 17th. Two loading spaces are proposed in the structured parking area.

Early Assistance has been requested for a project at 111 NE Killingsworth St:

Current code: Proposal is for 5 unit condominiums.

Early Assistance has been requested by Habit for Humanity for a project at 8124 N Interstate Ave:

More than likely – future code -with not a lot of impact to the site/project by the changes: New construction of 30 units of multi-dwelling housing development. It will be two (2) 3-story buildings to be constructed in two phases. All units will be sold as permanently affordable condo through the City of Portland preference policy. This project is to move through the GATR fast-track process with oversight from PHB.

The PSU Four+Montgomery building at 401 SW Harrison St has been submitted for Type III Design Review and Type III Conditional Use Review by SRG Partnership:

Construction of new 7-story, 174,000 sq ft classroom/lab/office building. See concurrent DZM, AD review (case # is: LU 18-151941 DZM, AD).

Construction of new 7-story, 174,000 sq ft classroom/lab/office building. See concurrent Conditional Use Case (LU 18-151969).

A project at 5055 N Greeley Ave at the Adidas Campus has been submitted for Type II Design Review by Hacker Architects:

The project proposes a new structure (identified as the “Intersection”) located between two existing buildings (Identified as Buildings B and C) on the Adidas campus. The proposal also includes a new pedestrian plaza along N Greeley Ave.

A project at 7661 SW Capitol Highway has been submitted for building permit review:

Four story 39 unit mixed use building with ground floor commercial shell.

A building permit was issued to Soderstrom Architects for an addition to St John Fisher Parish at 4567 SW Nevada St:

Addition to existing building to add new parish hall; renovation of existing rectory (R3 occupancy); new site improvements include parking, landscape and storm water facility

A building permit was issued to FFA Architecture & Interiors for the 10th & Yamhill Smart Park Renovation:

Addition to existing parking garage; stair and elevator towers to be removed in all 4 corners; stairs and elevators to be replaced at 2 corners; retail additions at 2 corners; maintain occupancy of parking garage and parking enforcement office during construction. Reconfigure first floor layout including partitions for shell tenant spaces and addition to first floor shell tenant spaces at northeast and southwest corners. Repair and maintenance throughout parking levels. Accessibility upgrades. ***mechanical permit separate***

A structural permit was issued to GBD Architects for SW 3rd & Ash:

STR 01 – Partial permit for excavation, shoring, foundation, structural shell through level 2 and all under slab and perimeter utility for the project. One level below parking with 6 stories above grade

A building permit was issued for a project at 1610 SE Tacoma St:

New 3 story, 12 unit apartment building with attached trash enclosure, includes associated sitework *** w/ 17-264915-MT ***

A shoring permit was issued for a project at 6315 SW Canyon Ct:

Partial permit for temporary shoring wall and mass grading for Buildings 1, 2 & 4

A building permit was issued to Scott Edward Architecture for a project at 5905 SE Belmont St:

New single story dental clinic and surrounding site improvements; shell only.

A building permit was issued to Mackenzie for a project at 2922 SE 82nd Ave:

Construct new 3-story self storage building; 1st floor. 3 separate future tenant spaces and storage; 2nd & 3rd floor storage only; and associated site work *** mechanical permit 17-196247mt ***

Renovation of 10th & Yamhill Smart Park Approved (images)

The Design Commission has approved plans by the Portland Bureau of Transportation and Prosper Portland to renovate the 10th & Yamhill Smartpark Garage. The project is being designed by FFA Architecture and Interiors, and is intended to address ADA and seismic deficiencies  in the existing structure, as well as improve the ground level retail experience.

10th & Yamhill Smart Park

Read More

Metro Reports: 10th & Yamhill Smart Park, 203 NE Grand, Providence Park, and more

10th & Yamhill Smart Park

Building permits are under review for the renovation of the 10th & Yamhill Smart Park Garage

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers November 20th to November 27th, 2017.

Early Assistance has been requested by Carleton Hart Architecture for a project at 320 NW Hoyt St:

Renovation of existing (vacant) 3-story warehouse to be used as a shelter

Early Assistance has been requested by BAMA Architecture & Design for a project at 1537 SE Morrison St:

Future code – Evaluation of options for development of property.

A Pre-Application Conference has been scheduled to discuss a project at 12400 SE Schiller St:

Future code – Two planned multi-dwelling unit buildings with associated utilities, parking, and walkways on two existing legal lots of record.

A Pre-Application Conference has been scheduled by Ankrom Moisan Architects to discuss a project at 203 NE Grand Ave:

Current code: New eight story mixed use project with apartments on levels 2-8. Ground floor retail. Amenities include a lounge, fitness, leasing, bike storage and bike lounge, pet area and pet wash area.

A Pre-Application Conference has been scheduled by GBD Architects to discuss a project at 236 SE Grand Ave:

Current code – Proposal to build seven story B occupancy office building on the 1.2 block between SE Pine and SE Ash on SE Grand Ave. The structure will be approximately 100 feet tall with a gross area of approximately 107,000 square feet.

The renovation of 10th & Yamhill Smartpark Garage has been submitted for building permit review by FFA Architecture & Interiors:

Addition to parking garage. Replace northeast and southwest stair and elevator towers with new (demo’d under permit 17-273719-co). Demolish northwest and southeast stair and elevator towers. Reconfigured first floor layout including partitions for shell tenant spaces and addition to first floor shell tenant spaces at northeast and southwest corners. Repair and maintenance throughout parking levels. Accessibility upgrades. ***mechanical permit separate***

Alteration to parking garage. Selective demolition of the northeast and southwest corner stair and elevator towers, and demolition of interior partitions on the first floor tenant spaces. Related selective demolition of mechanical, electrical and plumbing systems.

A structural permit was issued to Allied Works Architecture for the Providence Park Expansion:

STR 02: All micropiles shown on sheets S200C, 2001A, and 2002A; Shotecrete slabs on the hillside shown on S2001A at the north and south ends. This includes pile cap tie reinforcement that would be located within the shotcrete slabs.

10th & Yamhill Smartpark Receives Design Advice (images)

Plans by the Portland Bureau of Transportation and the Portland Development Commission to renovate the 10th & Yamhill Smartpark Garage have received Design Advice. The project is being designed by FFA Architecture and Interiors. The project is intended to address ADA and seismic deficiencies in the existing structure, as well as improve the ground level retail experience.

10th & Yamhill Smartpark

Read More

Metro Reports: Stark St Apartments, Tru by Hilton, Derby NW, and more

Ankrom Moisan’s Stark Street Apartments at 12613 SE Stark St will include 153 units of affordable housing

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Design Advice has been requested by FFA Architecture and Interiors for alterations to the 10th & Yamhill Smart Park Garage:

Alterations to smart park garage that include replacing existing stairways/elevators, new signage and awnings, reconstructed enterances and row encroachments. Green roofs are under consideration for new areas.

Design Advice has been requested by MCA Architects for a project at NW 13th & Savier:

Design Advice Request for 5-story self storage facility with ground floor retail

Early Assistance has been requested by LRS Architects for a project at 5734 E Burnside St:

4-story apartment building with ground floor retail and at grade parking. 3 stories of studio and 1-2 bedroom units.

Early Assistance has been requested by EPR Design for a project at 3244 SE 120th Ave:

New 16 unit building with pervious pavement and drywells for storm water runoff, 9 parking spaces in a garage and 7 spaces on private street. Seeking to meet Community Design Standards.

Early Assistance has been requested by DMS Architects for a project at 718 NE Dekum St:

Keep existing home on property and develop a new 3 story 6 unit apartment building with ground floor retail might want to divide the property located in the Woodlawn Conservation District

A Pre-Permit Zoning Check has been requested by Ankrom Moisan Architects for the Stark Street Apartments at 12613 SE Stark St:

Proposal for 153 units of affordable housing supported by home funds issued by PHB. The project is made up of two four story buildings with on-site parking to residents.

The Tru by Hilton at 7101 NE 82nd Ave has been submitted for Type III Conditional Use Review by JRA Architecture & Planning:

Proposal is to construct 98 guest room four story wood frame on-site parking suites hotel with pre-prepared breakfast (ho restaurant) on existing red lion hotel site. Remove existing 68 room red lion hotel annex in proposed construction area.

Interior alterations to the Meier & Frank Building have been submitted for permit review by Bora Architects:

Interior alteration -demolition of interior partitions, finishes, and associated materials. Demolish dedicated MEP systems serving current Macy’s tenant space. All work will be coordinated to ensure cotinuous operation of hotel floors above

A project at 5515 NE 17th Ave has been submitted for building permit review by CIDA Architects:

Construct new 3 story, 15 unit, apartment building with attached trash enclosure and associated site work

The Derby NW apartments at 1015 NW 16th Ave have been submitted for building permit review by Koz Development:

Construct 6-story mixed use 128 unit apartment building, on ground floor retail tenant space, bike storage, garbage room, electrical room and residential units and associated site work

A project at 1724 NE 45th Ave has been submitted for building permit review by Deca Architecture:

New 3 story w/ basement, 12 unit apartment building , includes associated sitework – prelim mtg 16-289387 bd –

A project at 9109 NE Cascades Parkway has been submitted for building permit review:

New three story office building with onsite parking, 204 S.F. Detached trash enclosure, includes associated sitework *** w/ MT permit and trash enclosure permit (17-117593-CO) ***

A building permit was issued to Koz Development for the 2165 SW Yamhill St apartments:

Construct new 4 story 30 unit apartment building; bike storage on lower floor mezannine level; associated site work

Metro Reports: 4W Tower, Press Blocks, 10th & Yamhill Garage, and more

Context drawing for the proposed 4W tower by ZGF Architects

Context drawing for the proposed 4W tower by ZGF Architects

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Design Advice has been requested by William Kaven Architecture for a project on Old Town Chinatown Block 33 at 125 NW 4th Ave:

Discuss a full block mixed use development Full Block mixed use development with 5 levels of residential over 4 levels office over ground floor retail/market and lobby with 2 levels of below grade parking.

Early Assistance has been requested by Waechter Architecture for a project at 1610 SE Tolman St:

Construction of a new Commercial Mixed Use building to share a site with existing Dairy Queen drive through restaurant.

Early Assistance has been requested for a project at 3249 SE Division St:

Proposal is for a five story building consisting of four floors of residential units a top ground floor retail and vehicle parking. 19 parking spaces and one loading bay are proposed.

Early Assistance has been requested by Brett Schulz Architect for a project at 4303 N Albina Ave:

Proposal is to build a community of eight micro houses on two 5,000 sf sites. Existing dwelling to remain.

Early Assistance has been requested for a project at 2231 NW Pettygrove St:

Proposal is to build micro unit apartments with kitchens in each apartment and do a density transfer of 4:1 FAR.

Early Assistance has been requested by GBD Architects for the PCC Child Development Center at 11900 SW 49th Ave:

Development of Child Development Center – includes alterations to an existing building on the campus (south classroom building) as well as the construction of a new free-standing building.

A Pre-Application Conference has been scheduled by FFA Architecture & Interiors to discuss the 10th & Yamhill Smart Park Renovation:

Pre-application conference to discuss the alterations proposed to the Smart Park Garage that include replace existing stairways/elevators, new signage and awnings, reconstruct the entrances and ROW encroachments. Green roofs are under construction for new areas.

A project at 1340 SE 9th Ave has been submitted for a Type III Conditional Use Review by Scott Edwards Architecture:

Existing 1 and 2 story factory use building on 2 blocks to be re-used and upgraded for creative office, factory, and small retail.

A project at 408 SE 105th Ave has been submitted for Type II Design Review:

Proposal is for a 13-unit apartment buidling.

The 4W tower at 419 SW Washington St has been submitted for Type III Design Review by Greystar Real Estate Partners:

New building – with 400 market-rate residential rental units with below grade parking.

The Press Blocks at 817 SW 17th Ave have been submitted for Type III Design Review by GBD Architects:

Proposal is to develop one full and one-half block for residential tower and office plus retail. 447 below grade parking space and 577 bike parking spaces.

The SW 3rd & Ash mixed use building has been submitted for Type III Design Review by GBD Architects:

New 6-story mixed-use building with approx. 8640 sq. ft of ground-level retail, 133 market-rate residential units and 63 below-grade parking spaces. proposed.

A project at 7707 SE Alder St has been submitted for building permit review:

Construction of new 6 plex building, 3 story, includes site utilities, detached trash enclosure is less than 120 sf

A project at 7667 N Westanna Ave has been submitted for building permit review:

Construct new 3 story 4 plex with tuck under garages, 2 units on lowest level, 2 units on main level that include upper level, no detached trash enclosure shown on plans, includes associated site work

A project with two buildings at 1329 N Skidmore St has been submitted for building permit review:

New 3 story apartment building with 12 units

New 3 story apartment building with 12 units

A project at 6035 NE Flanders St has been submitted for building permit review:

Construct 3 story, 4 plex building with 2 tuck under garages, 2 units on lowest level, 2 main floor units with upper levels above, no detached trash area, includes associated site work

A project at 2027 SE Harold St has been submitted for building permit review:

Construct new 3 story (4) unit apartment building with associated site work

A building permit was issued for the Tesla Showroom at 4330 SW Macadam Ave:

Remove interior partition walls, new walls to create showroom, offices, storage. New exterior ada ramp, new exterior door on south elevation.

A building permit was issued for a project at 4405 SE Belmont St (previously 4335 SE Belmont St):

New 4 story, 63 unit apartment building with onsite parking, site utilities and landscaping

A building permit was issued to Encore Architects for a project at 1411 NW Quimby St (previously 1400 NW Raleigh):

New 6-story apartment building, 135 units, 11 live/work units, ground level retail and parking.

Metro Reports: 21 Astor, 710 E Burnside, SW Park & Columbia, and more

21 Astor, designed by FFA Architecture for Robert Ball Companies

21 Astor, designed by FFA Architecture for Robert Ball Companies

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

A Pre-Application Conference has been scheduled and Design Advice requested by GBD Architects for a project at SW Park and Columbia:

8-story multi family 100-110 unit residential project with 33% affordable housing.

A demolition permit was issued for the existing structure at 710 E Burnside St:

Demolish/deconstruct existing restaurant building, cap sewer, remove all debris *** non-residential comprehensive plan designation. Not subject to 35-day demolition delay. ***

A project at 5454 NE 14th Pl has been submitted for building permit review:

New 4-story apartment building to include 15 dwelling units. Main floor to include parking garage and bike parking and associated site work.

A project at 9525 N Lombard St has been submitted for building permit review:

Construct new 2 story (7 unit) apartment building with associated site work

A building permit was issued to FFA Architecture + Interiors for a 21 Astor at 921 NW 21st Ave:

New 4 story mixed use building, (2) ground floor retail spaces and (31) parking spaces, 27 apartment units on floors 2-4.

A building permit was issued for a project at 1526 N Holman St:

Construct new 3 story (6) unit apartment building; with associated site work; detached trash enlosure less than 120 sq ft

Weekly Roundup: Overlook Pointe fire, 10th & Yamhill Smart Park, Field Office, and more

10th & Yamhill Smart Park

Conceptual image of a renovated 10th & Yamhill Smart Park garage (image by FFA Architecture & Interiors)

The Portland Development Commission received three offers for Centennial Mills, according to The Oregonian. All three offers, valued at $1,000, $100,000 and $3.45 million, were rejected. The redevelopment agency will now consider “how/whether to reengage the market”.

The DJC reported that the under construction Overlook Pointe condominium development at 5425 N Minnesota Ave was burned down in a fire* early Wednesday morning.

The PDC voted to sell property at 1053–1201 NW Naito Parkway to The Wolff Company for $9 million. The Oregonian reported that the developer plans to build 340 apartments on the site, 68 of which would be affordable for at least 10 years.

KGW covered the 1,200 apartments coming to the area in and around the Con-way Masterplan area in NW Portland. Construction is underway on Blocks 294E and 295E and the Leland James Buildingwhich are following on from the LL Hawkins and Slabtown MarketplaceImmediately outside of the masterplan area is Q21, which is nearing completion.

The Portland Tribune wrote about the “new mood in Chinatown“, which after decades of divestment might be seeing a change in its fortunes. The Society Hotel opened last year, and will soon be joined by the newly renovated Mason Erhman Building Annex, Overland Warehouse Company Building and Grove Hotel.

The Portland Mercury profiled Swift Real Estate Partners, the San Francisco Investment Firm that is “Snatching Up Old Town Real Estate“. The company’s acquisitions include the New Market Theatera historic building adjacent to the Skidmore Fountain that could receive a significant addition.

Project^’s Field Office will create a “300,000-square-foot urban campus“, according to the Portland Business Journal. Construction recently started on the Hacker-designed buildings at NW Front and 17th.

More than 1,000 people applied for the 65 housing units available to people displaced from North and Northeast Portland, according to The Oregonian.

The City is planning a $25 million renovation of the 10th & Yamhill Smart Park, according to the Portland Business Journal. The scope of the project will include addressing seismic and ADA deficiencies in the existing structure.

Three new surf shops are set to open in the next year, reports The Oregonian. These include Cosube, which will open in Slate at the Burnside Bridgehead, and Leeward Northwest Surf & Sea, which will open in New New Crusher Court at 2450 NE Sandy Blvd.

According to the Portland Business Journal, furniture retailer Room & Board will open next year in the Pearl District’s newly renovated Fisk Tire Company Building.

The Business Tribune wrote about a day in the life of the team at OHSU working on the Knight Cancer Research Building.

*This article will be unlocked for the rest of this week. After this week it will only be viewable by DJC subscribers.