A permit is under review for an 11-story affordable housing development at 2059 SW Park Ave. The building, designed by Tahran Architecture & Planning, will use modular construction.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers October 18th, 2021 to October 24th, 2021.

Early Assistance has been requested by YBA Architects for a project South of 9330 SE Harold St:

The project consists of two buildings. Building A is a the 129,095SF 5-story, Type IIIB with 162 units of varying in size. The building fronts SE 92nd Avenue and creating an ¿L¿ shape around a residential green. Building B consists of seven 2-story town homes totaling 7,452SF. The main building will house a commercial gym at the SE corner, commercial co-working space in the center on 92nd, and a commercial office at the NW corner. Stormwater will be disposed through drywells , located either in the parking lot, or the landscape area in middle of the site.

Early Assistance has been requested for a project at 6698 NE MT St Helens Ave:

Applicant wishes to develop a car dealership, which may include (a) sales and leasing office (b) interior vehicle display (c) vehicle storage (d) vehicle repair facility and (e) other accessory uses such
as car wash on one or more of the development sites.

A Pre-Application Conference has been scheduled to discuss a project at East of 12395 SW Clara Ln:

52-bed residential care facility on a vacant property in the R10 zone – Conditional Use Review

A project at 1460 NE Prescott St has been submitted for building permit review by Koble Creative Architecture:

PDOX PS – new 3 story mixed-use building with basement. Basement storage, first and second story retail spaces, and 3rd story dwelling unit. Includes associated site work.

A project at 4961 SE 73rd Ave has been submitted for building permit review by McGuirl Designs & Architecture:

PDOX PS – Building A – new 3-story, 16-unit apartment building with associated site with/ w/ 21-092509-CO

PDOX PS – Building B – new 3-story, 14-unit apartment building with associated site with/ w/ 21-092506-CO

The SW Park Apartments at 2059 SW Park Ave have been submitted for building permit review:

SW PARK APTS – New 11-story, 89-unit prefabricated modular building utilizing mass plywood panels and light gauge steel; no parking; includes associated site work *** w/21-069768-MT ***

A building permit was issued to Mithun for Building A, a part of the Pop Blocks Phase 1A:

PEPSI BLOCKS – BUILDING A – New 8-story mixed-use building with 219 apartment units, residential amenities, retail spaces, and underground parking; includes new Woonerf, plaza, and associated site work. Project does NOT use Type III Code Guide. *** w/20-129212-MT ***

Metro Reports: Stark Family Housing, Analog, 1010 SE Ash, and more

The Stark Family Housing at 160th and Stark will include 93 units of affordable housing, with a mix of 1-, 2- and 3-bedroom units. The building design is by Holst Architecture for project owner Human Solutions.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers November 9th, 2020 to November 15th, 2020.

Early Assistance has been requested by Viking Development for a project at 6343 N Lombard St:

Development of net zero 3 story, 12 unit, 7500 GSF multifamily. Likely stormwater infiltration via drywell.

Early Assistance has been requested by Emerio Design for a project Northwest of 2200 NW Front Ave:

Construction of an office building

A project at 2057 SW Park Ave has been submitted for a Type II Design Review by Tahran Architecture & Planning:

100 day review timeline. New construction 91-unit affordable housing building on a 6,016 square foot parcel. The building is an 11-story structure, modular units, prefabricated structure utilizing mass plywood panels and light gauge steel for a Type IV B building

A project at 12102 SE Division St has been submitted for building permit review:

PDOX PS – New shell building (pad 2) w/20-159383-CO (BK building), 20-203182-CO (trash enclosure) & 20-203177-MT

PDOX PS – TI for existing tenant; no change of occupancy; reduce size of restaurant to reconfigure drive-thru, and install second drive-thru pad to the east; additional site work to include new paving, parking, striping, landscaping, and bike racks w/20-203182-CO (trash enclosure), 20-203184-CO (pad 2 shell building) & 20-203177-MT

1010 SE Ash has been submitted for building permit review:

TROY LAUNDRY NORTH – New 6-story, mixed-use building with one below grade parking level, ground floor retail and amenity, outdoor roof amenity, and residential/extended stay units above *** w/ 20-197604-MT ***

The Stark Family Housing at 16015 SE Stark has been submitted for building permit review:

PHB – Construction of a new 5 story, 93 unit affordable housing building with ground floor amenity spaces and 26 surface parking spaces/1 Type B loading space. (with 20-206651-MT)

Analog at 1835 N Flint Ave has been submitted for building permit review:

ANALOG – New 7 story apartment building with 134 units, ground floor lobby, amenity, open courtyard, residential units and parking. Upper floor levels all residential with 7th floor deck. Separate outbuilding for small Sauna and storage use. ***Review with 20-188851-MT & 20-189915-CO, 20-190648-MT

A building permit was issued to Brett Schulz Architect for a project at 330 NE Dekum St (previously 308 NE Dekum St):

New 4 story 39-unit apartment building, some units with outdoor patio’s, interior trash enclosure, and associated site work

Metro Reports: 2057 SW Park Ave, 800 SW 13th Ave & 5803 N Greeley

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers June 22nd, 2020 to June 28th, 2020.

Design Advice has been requested by Tahran Architecture & Planning for a project at 2057 SW Park Ave:

The proposal is to build an 89-unit affordable housing building on a 6,016 square foot parcel at 2055-2057 SW Park Avenue. The building is an 11-story structure, modular units, prefabricated structure utilizing mass plywood panels and light gauge steel for a Type IV B building.

Early Assistance has been requested by GBD Architects for a project at 800 SW 13th Ave:

Study development opportunities of Commercial Office, Residential or a mixed-use of Residential and Commercial Office uses with underground parking.

A project at 5803 N Greeley Ave has been submitted for building permit review:

PDOX PS – new 3 story 14 unit apartment building with associated site work; detached trash enclosure < 120 sf; w/20-150640-MT

Metro Reports: Lincoln High School, 3219 SE Milwaukie, 5145 SE Mcloughlin, and more

The first building permit for the new Lincoln High School was issued.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers January 27th, 2020 to Februrary 2nd, 2020.

Design Advice has been requested by SERA Architects for a project at 2250 NW Flanders St:

6 story apartment building with approximately 200 units in the Northwest Plan District and Alphabet Historic District. Non-contributing. Stormwater disposal method TBD

Early Assistance has been requested by DECA Architects for a project at 5505 SE 136th Ave:

New construction of a 6,425 sq ft, 2-story apartment building with 5 dwelling units and a new driveway (no commercial units). Adjustment to setback is needed.

Early Assistance has been requested by Tahran Architecture and Planning for a project at 3219 SE Milwaukie Ave:

Proposal to build a new 4-story apartment building with a total of 44-46 units of affordable housing. Stormwater disposal is proposed to be a storm water planter.

Early Assistance has been requested by Edge Development for a project at 5527 N Greeley Ave:

New 12-unit, 3-story multi-family residential building. No on-site parking provided. A drywell shall be proposed for stormwater retention.

A Pre-Application Conference has been scheduled by Carleton Hart Architecture to discuss Multnomah County’s project at 333 SW Park Ave

Renovation of existing building and adjacent lot

A project at 2047 NE Davis St has been submitted for a Pre-Permit Zoning Check:

New fourplex apartment to create a total of 6 dwelling units on the lot. Proposed stormwater disposal method is not included in this pre-check.

A project at 2321 SE 89th Ave has been submitted for a Pre-Permit Zoning Check:

3 new fourplex apartments, to create a total of 13 dwelling units on the lot. Proposed stormwater disposal method is not included in this pre-check.

A project at 2135 NW 29th Ave has been submitted for a Type III Design Review, by Jones Architecture and Waechter Architecture:

Development of eight 15,000SF mass-timber apartment buildings (type 3-B); each 5 stories with parking. Each to have their own building permit per OSSC 2019, but processed as one Type3 LUR per Pre-App direction. Modifications requested to Ground Floor Window requirement and Pedestrian Access requirement.

A project at 2011 NE 47th Ave was submitted for building permit review:

New 2 story 5 unit apartment building.

A project at 5145 SE Mcloughlin Blvd was submitted for building permit review by Fosler Portland Architecture:

New 19 unit apartment building with associated site work; no on site parking; mechanical permit separate

A foundation permit was issued to Bora Architects for the new Lincoln High School:

FND 01 – New foundations, slab on grade and under slab utilities for a 6 story, 291,000 sf high school.***review with 19-218828-MT

Metro Reports: Bezel, Sellwood CVS, Modera Woodstock, and more

A building permit was issued for the Bezel Apartments at NE 15th and Alberta.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers May 13th to May 19th, 2019.

Early Assistance has been requested by Works Progress Architecture for a project at 737 SE Sandy Blvd:

Current structure is to be deconstructed. New construction will be a ground up office building which is expected to be 6 levels when finished. Project will absorb approximately 15′-20′ of the west and south portions of the current ROW. Street Vacation is requested. Stormwater could be mitigated through the use of a BES retention pond / bioswale / flow through garden at the southern point of the property, financed by the BES CWSP.

Early Assistance has been requested by Sum Design Studio for a project at 210 SE Madison St:

Project is a renovation of two buildings: one at 210 SE Madison Street and one at 226 SE Madison Street (the two smaller existing additions on the south side of 210 will receive no work). The two main buildings will function as a single building (circulation and infrastructure) and will be configured for future lease out. Improvements include new vertical circulation (stairs and elevator), architectural finishes, fire and life safety systems (sprinklers, alarms, etc.) new egress routes and seismic upgrades. A new 5,000 SF penthouse will be constructed on the roof of the 210 building. Exterior improvements include repairs as needed, new windows and doors and paint. A improved parking lot at the SE corner of the site with new ramp, paving and landscaping.

A Pre-Application Conference has been scheduled by Hacker Architects to discuss a project at 2865 SE Division St:

Future design review application for a 10-unit, approximately 37,000SF multi-family project with a ground floor restaurant tenant space and 20 parking spaces. Parking is accessed from SE 28th. Outdoor space is provided in individual terraces and a common rooftop deck.

A Pre-Application Conference has been scheduled by Mortenson to discuss a project at 234 NW 14th Ave:

Demolition of existing single story 1/2 block (100’x100′ site); Construction of new 12 story hotel.

The Modera Woodstock at 4804 SE Woodstock Blvd has been submitted for a Type II Adjustment Review by Mill Creek Residential Trust:

Construction of a full-block mixed-use building with approx 195 residential units and 6,750 sq ft of ground floor commercial space (along Woodstock). Adjustment requested to High Ceilings (per 33.130.210.C.8).

A building permit was issued to Fosler Portland Architecture for the Bezel apartments at 1477 NE Alberta St:

New four story 18,866sf mixed use building 18 dwelling units above shell space, bike parking, lobby, and interior trash/recycling room, for residential and commerical green roof with rooftop deck ***separate mechanical permit required*** ***2/11/2019 cmeyer mandatory preconstruction meeting required prior to commencing work call 503-823-7273 to schedule***

A building permit was issued to Tahran Architecture and Planning for a project at 5605 SE Milwaukie Ave:

New 4 story, 30 unit with attached trash enclosure, includes associated sitework ***separate fire protection***

A building permit was issued to Barghausen Consulting Engineers for the Sellwood CVS at 8145 SE 17th Ave:

New single story retail building, parking lot, detached trash enclosure less than 120 sq ft floor area, stormwater facility, site improvements and utilities.

Metro Reports: Historic Multnomah County Courthouse, 5632 N Montana, 801 NE 21st, and more

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers April 29th to May 5th, 2019.

Early Assistance has been requested by Works Progress Architecture for a project at 5632 N Montana Ave:

New 5 story apartment building with ground floor residential and parking (120 units). Stormwater is assumed to be drywells.

A Pre-Application Conference has been scheduled by Tahran Architecture & Planning to discuss a project at 2057 SW Park Ave:

Proposal is for an 8 story building with a basement containing 84 affordable apartments. We anticipate using stormwater planters for stormwater disposal. We are applying also for a FAR bonus for all affordable units.

A Pre-Application Conference has been scheduled by GBD Architects to discuss the renovation of the Historic Multnomah County Courthouse:

The proposed project is a renovation of the existing, historic courthouse into a mixed-use building with new office and hotel program within the existing shell. The existing building is 249,588 gsf above grade with a 34,485 sf basement. The majority of the improvements are anticipated to be interior to the building. No net impervious area is being proposed. Stormwater disposal requirements / strategies to be discussed.

A Pre-Application Conference has been scheduled by Hacker Architects to discuss a project at 801 NE 21st Ave:

New 7-story multi-family residential building over 1 of below grade parking level. Total building will be 235,000 gross sf (195,000 sf FAR), 244 units, plus residential amenities. Inclusionary Housing will be triggered and provided on-site at standard rates. Stormwater treatment is anticipated on-site via drywells.

A project with two buildings at 7428 N St Louis Ave has been submitted for building permit review:

New 12 unit 3 story apartments ***mechanical separate permit*** see 19-159285-CO for identical bldg on adjacent lot

New 12 unit 3 story apartments ***mechanical separate permit*** see 19-159273-CO for identical bldg on adjacent lot

A project East of 400 SE 111th Ave has been submitted for building permit review:

Construction of new 3-story triplex with associated sitework.

A building permit was issued to Fosler Portland Architecture for a project at 1627 SE Reedway St:

New 12 unit 2 story apartment building

Metro Reports: Troy Laundry, 3000 SE Powell, 5434 SE Milwaukie, and more

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers April 1st to April 7th, 2019.

Design Advice has been requested by Holst Architecture for the Portland Housing Bureau project at 3000 SE Powell:

Construction of a new 5-story structure (4-over-1) with approximately 175 affordable housing units, 7,000 sq ft of ground floor active uses and 30 parking spaces. There is 35 to 50 feet (or more) of undocumented fill across the site and is assumed that infiltration will not be allowed into this undocumented fill, a connection to the public combo sewer (Hierarchy Category 4) is the only option.

Early Assistance has been requested for a project at the Troy Laundry building at 1025 SE Pine St:

The Troy Laundry building at 1025 SE Pine is a historic landmark on the National Register of Historic Places. Decades after the original structure (the ‘Main Building’) was built, addition areas were added to the north part of the block. The remainder of the block is a surface parking lot.

If we purchase the property, we will renovate the Main Building. Ideally, this will include an internal renovation, exterior repairs that retain the historic character, and addition of a roof deck to the Main Building. We also expect to redevelop the north half of the site with new construction. This will involve removal of the structures built after Main Building was constructed and replacement with a new building (which will likely be flush with the main Troy Laundry building).

We recognize that this redevelopment project will require a Type III review and, therefore, a pre-application conference (and that this EA does not satisfy that requirement). We are seeking feedback only on the questions we submitted in order to assess initial feasibility during our purchase due diligence period.

A building permit was issued to Icon Architecture/Planning for a project at 6822 N Greenwich Ave:

New construction of 3-story, 9 unit apartments with a rooftop deck and associated site work *** floor & roof trusses to be a DFS *** mechanical permit to be separate ***

A building permit was issued to Tahran Architecture & Planning for a project at 5434 SE Milwaukie Ave:

Construct new 4 story with basement 28 unit; no parking; 40 sq ft trash enclosure; site work included 100% inclusionary housing

A building permit was issued to Fosler Portland Architect for a project at 1514 N Emerson St:

New 3 story 19 unit apartment building with enclosed bicycle parking.

A building permit was issued for a project at 3737 NE Columbia Blvd:

New construction of two 3-story self storage buildings connected with three hour wall with associated parking, utilities and landscape. (demo permit separate); 120 sq ft trash enclosure

Metro Reports: Pioneer Lavada Jones, Pepsi Redevelopment, Madison High School, and more

Pioneer Lavada Jones

Guerrilla Development’s Pioneer Lavada Jones project will include removing the roof on the existing NE Sandy Blvd building to create a new outdoor courtyard.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers May 28th to June 3rd, 2018. 

Design Advice has been requested by Mithun for the Pepsi Redevelopment at 2505 NE Pacific St:

Planned development for redeveloping the existing Pepsi Bottling Plant on Sandy Boulevard into market-rate and affordable housing, offices, retail/restaurant spaces, publicly-accessible open space, and associated underground parking.

A Pre-Application Conference to discuss the first phase of the project has also been scheduled:

Phase 1 of the Planned Development for redeveloping the existing Pepsi Bottling Plant on Sandy Blvd. Includes the renovation of the existing mid-century Pepsi warehouse, two new apartment buildings, below-grade parking and a new publicly-accessible Plaza.

Design Advice has been requested by Ankrom Moisan Architects for a project at 1515 SW Morrison St:

Proposed design replaces existing structure on the south half of the block with a mixed use, 20-story high-rise apartment tower. Ground floor features retail, lobby and amentiy spaces. Parking provided below grade.

Early Assistance has been requested by CityCraft Development for a project at 5020 NE Martin Luther King Jr Blvd:

New 7-story mixed use building with underground parking. They will need to go through a design review.

Early Assistance has been requested by Tahran Architecture & Planning for a project at 1603 N Willis Blvd:

Proposal for a four story with basement structure to house 49 affordable housing units using community design standards for a contributing site in Kenton Conservation District. Proposed storm drainage is a rain garden.

Early Assistance has been requested by Benner Stange Associates Architects Inc for a project at 1555 N Tomahawk Island Dr:

Proposal for a new single story three tenant building with two restaurant tenants and one hair salon.

Early Assistance has been requested by V3 Studio for a project at 4624 SW Dickinson St:

Proposal to add 58-89 new multi-family units to existing property that has currently 32 existing multi-family units.

Early Assistance has been requested for a project at 2124 NW Flanders St:

Request for early assistance meeting, zoning only for a site in Alphabet Historic District for a development including a new 3-4 story with daylight basement 14-19 units in a multi-dwelling building. The units will be a mix of 1 and 2 bedrooms. There are setback modifications to setbacks on east and west side lot lines and front lot line to exceed RH max building height of 25 feet. No on-site parking; short and long term bike parking to be included. Applicants know they will need a Pre-Application Conference but request this meeting with a planner only now.

A Pre-Application Conference has been scheduled by Doug Circosta Architect to discuss a project at 208 SE 148th Ave:

Proposal is for 160 new affordable rental living units with amenities and 63 parking spaces in RH zone, East Corridor Plan District.

A Pre-Application Conference has been scheduled to discuss the Madison High School Modernization at 2735 NE 82nd Ave:

Modernization project for Madison High School.

A project at 6015 SE 51st Ave has been submitted for building permit review by Studio 3 Architecture.

New construction 3 story 4 unit apartment building

A building permit was issued to Brett Schulz Architect for the Pioneer Lavada Jones building at 2636 NE Sandy Blvd:

Renovate existing 2-story build; shell only, no occupancy; demo interior partition walls and stairs; build new demising walls to create 10 future tenant spaces, new stairs, (5) new mezzanines, new deck, interior trash room and egress courtyard.

A building permit was issued for a project at 8410 SE 17th Ave (previously 8334 SE 17th Ave):

New construction of three story, 12 unit apartment complex with attached covered trash room and associated site work***w/17-281716-mt***

A building permit was issued to Urban Development Group for a project at 2580 SE Ankeny St (previously 2548 SE Ankeny St):

New 5-story, 96 unit apartment building; first floor includes loading/trash room, lobby, bike storage, electrical equipment room, and studios. Studios on remaining floors. W/17-214647-mt

Metro Reports: NE 106th and Halsey, Lincoln High School, Portland River Center, and more

A Pre-Application Conference was scheduled to discuss the Portland River Center

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers January 15th to January 21st, 2018.

Design Advice has been requested by Holst Architecture for a project at NE 106th and Halsey:

DESIGN HEARING – Current Code: Request for a Design Advice for a six story mixed use building including approx. 10,000 SF of ground floor retail, 9,000 SF of second floor office space and 75 apartments units including affordable housing units and 60 surface parking spaces.

Early Assistance has been requested by Köz Development for a project at 105 N Killingsworth St:

Future code: Proposal is for new 91 unit studio apartment building. 4-story, type VA construction. Stormwater will be rylnaged through green roof and discharged to city system.

Early Assistance has been requested by Merryman Barnes Architects for a project at SE 90th & Powell:

Future code: Proposal is to develop the property to accommodate a new +42,000 gsf clinic, a 52 unit senior housing building, and associated (shared) parking and landscaping. The senior housing project will likely be developed by another entity, and the site would be divided in order to allow for separate ownership and include a shared use agreement for the parking. No current plan for stormwater disposal at this time.

Early Assistance has been requested for a project at 835 SE 162nd Ave:

This site/project isn’t affected by the comp plan/zoning changes taking effect in May 2018.
Construction of six (6) 2-story buildings (townhomes and duplexes) of affordable housing (41 units units). The largest building is 26 apartments with community space and resident services spaces. New access drive with easement to 162nd. Stormwater treated on site with drywells, swales, and/or rain gardens.

Early Assistance has been requested by Waechter Architecture for a project at 5134 N Interstate Ave:

Future code: Proposal is for 60 apartments including afordable units. Amenity and retail space.

A Pre-Application Conference has been scheduled to discuss the Portland River Center on the OMSI campus:

A Pre-Application Conference to discuss construction of the Portland River Center. This facility will be operated by The Portland Boathouse, a non-profit organization. The facility will contain boat storage and staging areas, educational classrooms, a small office, workout spaces with showers and restrooms, and interior and exterior river-viewing areas. The building will have 29,000 square feet of floor area in a two story building and is located partially in the Willamette Greenway Setback.

A Pre-Application Conference has been scheduled by BORA Architects to discuss the new Lincoln High School:

Future code info for the rebuild Lincoln High School (demo and replace building). They will need a Type III DZ.

A project at SE 124th & Ash has been submitted for a Type II Adjustment Review by Ankrom Moisan Architects:

100-day review timeline: Construction of new 4-story workforce housing building with 175 units of affordable housing (all units), a community space, courtyard, two offices for support staff and 43 car parking spaces. They will be meeting community design standards. Adjustment requested for Loading Standards Placement, Setback and Landscaping (33.266.310.E).

A project at 5603 SE Milwaukie Ave has been submitted for building permit review by Tahran Architecture & Planning:

New 4 story, 30 unit with attached trash enclosure, includes associated sitework ***separate fire protection***

A project at 4126 NE Garfield Ave has been submitted for building permit review by Fosler Portland Architecture:

New 12 unit 2 story apartment building, includes pre-fab trash enclosure and associated sitework.

A project at 12350 NE Sandy Blvd has been submitted for building permit review:

New one story building for future restaurant (shell only – no interior walls, no concrete slab, no RTUs); includes restriping & upgrades to (E) parking lot & associated site work *** w/ 119 sq ft trash enclosure ***

A project at 4107 SE 28th Ave has been submitted for building permit review:

New 1 story restaurant on existing parking lot including seating area, kitchen, storage, toilet, trash room, bike parking, ramps and upper and lower deck patio. Infill existing driveway ***no occupancy in this permit***

A building permit was issued to Urban Development Group for a project at 5955 SE Milwaukie Ave (previously 6003 SE Milwaukie Ave):

New 4-story 54 unit apartment complex, trash enclosure within structure and associated site work

A building permit was issued for a project at 1375 N Wygant St (previously 4806 N Maryland Ave):

New construction of 10500sf, 6 unit 3 story w/basement apartment building with new trash/recycling, bike parking, and s-2 storage in basement ***separate mechanical permit required***

Metro Reports: 23 NE 151st, 5434 SE Milwaukie, 4220 SE 24th and more

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers November 6th to November 12th, 2017.

Early Assistance has been requested by Kasa Architects for a project at 23 NE 151st Ave:

Current code – 50 unit apartment building consisting of two and three room units, a community room, an office and a laundry room. On site amenities will include surface parking, a children’s play area, bike parking, and an enclosure for trash & recycling. On site storm water facility will be provided.

A project at 8116 SE Woodward St has been submitted for building permit review by Fosler Portland Architecture:

Construct new 3 story 19 unit apartment building; no parking; site work included; interior trash enclosre (sep mt)

A project at 5434 SE Milwaukie Ave has been submitted for building permit review by Tahran Architecture & Planning:

Construct new 4 story wit basement 28 unit; no parking; 40 sq ft trash enclosure; site work included 100% inclusionary housing

A project north of 4220 SE 24th Ave has been submitted for building permit review:

New single story building with (2) art studio spaces and (2) bathrooms.