Metro Reports: North 18, Choice Cambria Portland, 8736 N Willamette, and more

North 18
The first building permit has been issued for North 18. The six story apartment building will include 107 apartment units and 4,436 sq ft of retail space at the ground floor.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers July 19th, 2021 to July 25th, 2021.

Design Advice has been requested by SERA Architects for the Choice Cambria Portland at 135 NW Park Ave:

New Hotel, 5 (Type IIIB) over 1 (Type IA), 94,000 square feet, 174 units, 1 Type B onsite loading space, ecoroof and flow through planter for onsite stormwater.

Early Assistance has been requested by Wright Architecture for a project at 6519 N Montana Ave:

Review under code effective 8/1/21. New construction of a 7-story, approx. 55,000 sf affordable residential building (100% at 60% AMI) and associated site work. Drywell and swale stormwater facilities to be provided on site.

Early Assistance has been requested by Wright Architecture for a project at 4538 N Maryland Ave:

Review under post 8/1 code changes. New construction of a 7-story, approx. 122,000 sf affordable residential building (100% at 60% AMI) and associated site work. Drywell and swale stormwater facilities to be provided on site.

A project at 8736 N Willamette Blvd has been submitted for building permit review:

PDOX PS – new 3 story 22 unit apartment building with daylight basement, separate trash and bike parking buildings under 120 sq ft. w/ 21- 064599-MT

A project at 2111 N Rosa Parks Way has been submitted for building permit by West Architects:

PDOX PS – new 31 unit apartment building with associated site work.

A foundation permit was issued for North 18 at 1134 NW 18th Ave:

Concrete foundation for a new apartment building 

Metro Reports: Riverplace Parcel 3, 11005 E Burnside, 5327 NE Glisan, and more

A building permit was issued for the second phase of BRIDGE Housing’s Riverplace Parcel 3. Originally intended to be market rate housing, the six story building will now be affordable housing. The first phase, named The Vera, was completed earlier this year.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers December 7th, 2020 to December 13th, 2020.

Early Assistance has been requested by West Architects for a project at 5327 NE Glisan St:

New 27,671sf 30-unit apartment building

Early Assistance has been requested by Otak Inc and Palindrome Communities for a project at 5802 SE 92nd Ave:

The applicant seeks to develop a mixed-use project consisting of ground floor retail/commercial use and 4 floors of multifamily residential apartment use. The number of units is expected to be between approximately 37-42. The existing building on R135387 will be converted to ground floor commercial and residential units on the top floor It is assumed a mix of studio, one, and two bedrooms. On site parking will be evaluated. All required common/open space will be provided. Stormwater treatment has not yet been identified at this time.

Early Assistance has been requested by West Architects for a project at 2111 N Rosa Parks Way:

New 23,106SF, 30-unit apartment building with inclusionary housing.

A project at 11005 E Burnside St has been submitted for building permit by Mentrum Architecture:

PDOX PS – Construct new 3 story (29) unit apartment building with associated site work

Building permit were issued to Ankrom Moisan Architects for the second phase of Riverplace Parcel 3 at 2065 SW River Parkway:

New 6 story 5 over 1 Type IIIA and Type I wood apartment over concrete podium structure with ground floor commercial and daylight basement parking – 2nd 6 story tower permitted under 17-156297-CO, includes all site utility piping

PHB – BRIDGE HOUSING EAST TOWER – REV 03 – East building revised to meet program requirements for affordable housing. Fitness area removed, unit laundry removed and common laundry rooms added, mechanical system revised and electric heat added to units, unit bathrooms removed, foundation revision at NE corner, courtyard revised to include playground. See revision narrative for additional information.