Metro Reports: PDX PACR, 236 SE Grand, 2445 SE 8th, and more

Building permits were issued for the Parking Additions and Consolidated Rental Car Facility at Portland International Airport, designed by YGH Architecture.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers January 13th, 2020 to January 19th, 2020.

Design Advice has been requested by TVA Architects for a project at 236 SE Grand Ave:

Construction of a new 8 story office building. The building has 130,000 square feet of floor area with a height of 98’6″. Below grade parking with 39 stalls is proposed with access from SE Pine Street. Loading zone provided w/ separate entry off of SE Pine St. Stormwater will be managed on-site via eco-roof and drywells, if required. Alternate 6-story option also provided. This site is non-contributing.

Early Assistance has been requested by Concept Design And Associates for a a project at 2444 SE 90th Ave:

Proposal of 12 apartment units, 6 car garages or 6 parking spaces on site.

Early Assistance has been requested by LRS Architects for a a project at 2445 SE 8th Ave:

New 4-story, 80,000 sf industrial office building with penthouse. Included is planned multi-tenant industrial office and manufacturing space as well as the maximum allowable retail and traditional office space. The project will also contain on-site parking.

Building permits were issued for the PDX Parking Additions and Consolidated Rental Car Facility:

New 4 story airport operations office with rental car retail on the ground floor of the building, offices on floors 2-4, with associated site improvements related to the adjoining new 6 story PACR parking garage.

New 6 story parking garage with associated site improvements, exit helix ramp revisions, elevated roadway and bridge connections to existing P1/P2 and QTA buildings serving Rental Car and Long Term parking.

Metro Reports: PDX PACR, Old Fire Station Property, 8130 SE Woodward, and more

The $268 million PDX Parking Additions and Consolidated Rental Car Facility will include 2,225 long-term parking stalls and 2,071 stalls for rental cars.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers April 22nd to April 28th, 2019.

Early Assistance has been requested by WDC Properties for a project at 1604 SE Cesar E Chavez Blvd:

Remove duplex and construct new 50 unit apartment complex with IH for bonus.

Early Assistance has been requested by Carleton Hart Architects for a project at 1535 NE 17th Ave:

Proposed mixed use project adjacent to existing (to remain) church. Proposed development includes 6-story, 96 unit affordable housing, over 24,000sq ft office, church and classroom spaces. Street vacation requested.

Early Assistance has been requested by Allusa Architecture for a project at 422 NE Beech St:

New 8 unit hotel, hotel amenities include an exercise room/workspace on the ground floor. A separate ground floor office space is also provided.

Early Assistance has been requested by Quilici Architecture and Design for a project East of 6140 SW Boundary St:

Develop the property in phases as affordable rental housing and expansion facilities for Cedar Sinai Park, the non-profit senior living and care organization that owns the property.

A Pre-Application Conference has been scheduled by Abbasi Design Works for a renovation of the Old Fire Station Property at 510 NW 3rd Ave:

Restoration and small addition (of 1600 sq ft) to existing URM building, Engine House #2. Stormwater management to be managed using flow-through planters and water quality treatment.

A project at 2510 NE Sandy Blvd has been submitted for a Type II Adjustment Review:

5-story (with mezzanine) mixed-use building. Adjustment to Building Facades Facing Sandy Blvd standard (33.575.110).

Buildings permit are under review for the PDX Parking Additions and Consolidated Rental Car Facility:

New 4 story airport operations office with rental car retail on the ground floor of the building, offices on floors 2-4, with associated site improvements related to the adjoining new 6 story PACR parking garage.

New 6 story parking garage with associated site improvements, exit helix ramp revisions, elevated roadway and bridge connections to existing P1/P2 and QTA buildings serviing Rental Car and Long Term parking.

A building permit was issued to Koble Creative Architecture for a project at 4647 SE 40th Ave:

New 15 unit apartment building comprised of a two-story wing and a three-story wing with a connecting bridge; onsite stormwater

A building permit was issued to Mentrum Architecture for a project at 1834 NW 25th Ave:

Construct new 5 story 25 unit apartment building with no parking – see folder comments

A building permit was issued to Fosler Portland Architecture for a project at 8130 SE Woodward St:

Construct new 3 story 19 unit apartment building; no parking; site work included; interior trash enclosure (sep mt)