Metro Reports: 501 NW 21st, North of 4704 N Williams, and 1427 N Bryant

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers September 7th, 2020 to September 13th, 2020.

Early Assistance has been requested by Koble Creative Architecture for a project North of 4704 N Williams Ave:

The proposed project is a three-story residential building to be built on a vacant lot. This building is VB construction, sprinkled and consists of one stair and 13 apartments – (3) studios and (10) one
bedroom apartments.

A Pre-Application Conference has been scheduled to discuss a project at 501 NW 21st Ave:

Two story addition above existing restaurant (8 new apartments). No new impervious area and the roof currently drains to City system. This is a non-contributing resource.

A project at 1427 N Bryant St has been submitted for building permit review:

PDOX PS – Construct new 4 story 15 unit apartment bldg with associated site work

Metro Reports: Mann House, UP Franz Campus, Cathedral Village, and more

Innovative Housing plans to convert the Mann House in Kerns into affordable housing, with 39 units created in the existing building, 49 units in a new addition to the building and 40 units in a new building to the south.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers May 4th, 2020 to May 10th, 2020.

Early Assistance has been requested by Quilici Architecture & Design for a project at 6825 SW 45th Ave:

The Gabriel is a new 121 unit apartment building with 112 parking spaces. The building will be 4 stories of wood frame construction over 1 story of concrete construction. Levels 1-4 will be wood frame and contain residential uses. The basement parking level will be concrete and contain parking and 2 residential units. The ground floor (Level 1) includes the entry lobby and common area spaces. The building will have full automatic sprinkler systems with fire protection as prescribed by code.

Early Assistance has been requested by Koble Creative Architecture for a project at 1460 NE Prescott St:

New three-story mixed-use building and associated site improvements on occupied lot.

A Pre-Application Conference has been schedule by Emerick Architects to discuss the Mann House at 1021 NE 33rd Ave:

The conversion of an existing 51,000sf historic group-living complex into an affordable housing complex. With a new 36,000sf addition and a future, 32,000sf stand alone building to be added to the
site, a total of 128 new affordable housing units will be created. New dry wells and stormwater basins will be added to the site for on-site stormwater filtration.

Cathedral Village at 8614 N Crawford Street has been submitted for a Type II Adjustment Review by MWA Architects:

100-day review timeline. Adjustment requested to 33.130.222, Maximum Building Length, to allow the required 7′ porch to have its roof extend into the required 20′ setback. Adjustment requested to 33.130.242, Transit Street Main Entrance, for an entrance required every 200′ of building length. Cathedral Village Apartments, 4-story apartment building with 110 affordable family apartments. The unit mix will be (11) 3-bedrooms, (45) 2-bedrooms, (37) 1-bedrooms and (17) studios. There will be resident services on the ground floor and 37 parking spaces. There is a basement level at the NW corner of the building that will house bike parking and storage.

A building permit was issued to Waechter Architecture for a project at 4224 N Mississippi Ave:

New 3 story mixed use building, group B offices on first and second floor, (1) R-3 apartment on third floor, includes associated sitework *** mechanical permit separate ***

Buildings permits were issued for buildings on the University of Portland Franz Campus (also known as the River Campus) at 6210, 6320 and 6350 N Van Houten Pl:

Track & Field complex including a 523 seat covered Grandstand (Part C on Plans): Construction of a new Collegiate Track & Field Facility including 6 lighting poles. See Comments

New 12,880 sf Boathouse and Environmental Lab building w/ 2,389 sf mezzanine. Work includes utility infrastructure, stormwater facilities, grading, paving, sitework & site lighting, and Greenway trail. See Comments

New single story, slab on grade, 46,682 sf physical plant with related mechanical, plumbing, electrical, and site work. Type II B Non-combustible construction, fully fire sprinklered. Separate PT and ET required. See Comments

Metro Reports: Pearl Building East, Atomic Orchard, Society RCP, and more

A building permit is under review for the Atomic Orchard on NE Sandy Blvd.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers November 18th to November 24th, 2019.

A Pre-Application Conference has been scheduled by TVA Architects to discuss a project at 2997 SW Moody Ave:

New mixed-use project in two buildings, with residential units above ground floor retail and at-grade level parking. The construction is 5 levels of 3B over 2 levels of 1A on one of the buildings, and the construction is 10 levels of 1A on the other building. Stormwater management to be determined.

The Atomic Orchard at 2510 NE Sandy Blvd has been submitted for building permit review by Brett Schulz Architect:

New 5 story 49-unit multifamily apartment building with ground floor retail and one accessible dwelling unit in attached ground floor annex building, includes associated site work *** w/19-193113-MT ***

The Modera Woodstock at 4804 SE Woodstock Blvd has been submitted for building permit review by Leeb Architects:

MODERA WOODSTOCK – New 5-story, 194 unit apartment building with one level below-grade parking and ground floor commercial spaces; includes associated sitework *** w/19-247370-MT ***

A project at 14507 E Burnside St has been submitted for building permit review by Doug Circosta Architect:

New 3 story 22 unit apartment building with office and common laundry room

New 3 story 24 unit apartment building with associated site work

A project at 115 N Going St has been submitted for building permit review by Urban Development Group:

New 3-story 6-unit apartment building with associated site work. Detached trash enclosure < 120sf ***mechanical permit separate***

A project at 5105 SE Woodstock Blvd has been submitted for building permit review:

New 3-story, 28-unit apartment building with interior trash enclosure, bike storage room and short-term bicycle parking.

The Society RCP apartments at 1435 NE 62nd Ave have been submitted for building permit review by Koble Creative Architecture:

New 3-story, 3-unit apartment building, including interior trash, associated sitework and on-site stormwater management.

The Pearl Building East has been submitted for building permit review:

New 7-story mixed use high-rise office building with three levels of underground parking garage and a penthouse amenity space *** w/19-237841-MT ***

Building permits were issued for a project at 408 SE 105th Ave:

Building 1 of 3 new apartment buildings, two stories with two units (see comments), includes associated site work *** 18-270002/04-CO & 18-280941/44/45-MT ***

Building 2 of 3 new apartment buildings, three stories with six units, includes associated site work *** w/18-269978-CO & 18-270004-CO & 18-280941/44/45-MT ***

Building 3 of 3 new apartment buildings, three stories with five units and community room, includes associated site work *** w/18-269978-CO & 18-270002-CO & 18-280941/44/45-MT ***

Metro Reports: Broadway Corridor, Society 42, Findley Commons, and more

A building permit is under review for Ethos Development’s Society 42 apartments.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers October 28th to November 3rd, 2019.

Early Assistance has been requested for a renovation and addition to the University of Portland Physical Plant Building:

Complete renovation of the Physical Plant building that will also include an extensive addition. A pedestrian plaza will replace the existing upper parking lot and connect to the main campus quad east of Shiley Hall. A few heritage trees will be preserved to help define public outdoor space. A new outdoor plaza space will be created on the west side of the building to support student project space and provide on grade access to Level 2. A new building mounted canopy is planned to create covered outdoor work space ouside the Adaptable Large Projects spaces on Level 1, on the north side of the building. Demolish much of Level 3 of the existing building and then expand it and build a new Level 4 on top. A new parking garage is proposed to be located along the west bluff, and will incorporate four levels of teired parking (accommodating 208 standard size parking stalls and 9 ADA sized stalls. This building also includes storage, electrical, and mechanical rooms on the lowest level.

A Pre-Application Conference has been scheduled by Koble Creative Architecture to discuss a project at 232 NE 97th Ave:

A Pre-Application Conference to discuss construction of a ten-story, 309,060 square foot mixed use building. There are approximately 317 residential units and 3,565 square feet of ground floor commercial space. A proposed new public street, NE Davis Street, would run east/west along the southern edge of the property. Below grade structured parking is proposed with 119 spaces. The access to the parking is from NE Davis.

The Broadway Corridor redevelopment has been submitted for a Type III Central City Master Plan:

Central City Master Plan with an adjustment requested to required active use zones on Lovejoy and Hoyt Streets.

Findley Commons at 5415 SE Powell Blvd has been submitted for a Type III Conditional Use Review:

100-day Review Timeline. The applicant is proposing to construct a new residential structure that includes 20 multi-family units and 15 group living units and will reduce the parking area on the site from 50 spaces to 34 spaces. The applicant is also seeking a lot confirmation to establish four existing legal lots that would compose (and create) a discrete area for the residential project. Parking would be shared between the residential and church uses.

The Society 42 apartments at NE 42nd & Prescott have been submitted for building permit review by Koble Creative Architecture:

New 3 story apartments containing (3) dwelling units; (1) on each floor with (6) sleeping units on the main level; sleeping units have access to cooking facility in main level dwelling unit; interior trash enclosure; associated site work to include patio, landscaping and storm water management; no on site parking; new retaining wall along west and south property line

A building permit was issued to Architecture Building Culture for a project at 6712 N Montana Ave:

New 3 story, 11 unit apartment building. Main floor to include lobby, bike room, and 3 apartment units, 4 units each on 2nd floor and 3rd floor. Includes site work, landscaping, bike parking and covered trash area ***w/ 19-130244-MT***

A building permit was issued for a project at 7171 SE Knight St:

New construction of 3 story, 12-unit apartment building, includes associated sitework

Metro Reports: 1336 E Burnside, Rocket Empire Machine, 804 SW 12th, and more

Guerrilla Development’s Rocket Empire Machine project includes the adaptive reuse of a 1949 building into four micro restaurants and a bar, along with the construction of an adjacent two story apartment building with 11 units.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers June 10th to June 16th, 2019.

Design Advice has been requested by Mortenson for a project at 234 NW 14th Ave:

DESIGN HEARING – Construction of a 12-story hotel. The proposed height is 124′. No off-street parking is proposed. A service bay is proposed with access from NW 14th Ave.

Early Assistance has been requested by Koble Creative Architecture for a project at NE 42nd & Prescott:

Construction of a new 3-story building for residential co-living, with associated site work

Early Assistance has been requested for a project at 278 SW Arthur St:

New 2-story office building with parking lot. Partial street vacation requested

Early Assistance has been requested by Rendina Healthcare Real Estate for a project at 804 SW 12th Ave:

A mixed use 220,000sf building with ground floor retail, four to five levels of medical office with residential above. Limited parking either below or above grade.

The Rocket Empire Machine at 6935 NE Glisan St has been submitted for a Type II Adjustment Review by Brett Schulz Architect:

Requesting adjustment to 33.130.242 for a transit-street facing main entrance. Renovation of an existing 1949 building (CO 18-244579) into (4) micro-restaurants and (1) bar with shared indoor and outdoor seating, including a seismic upgrade to the existing structure and two small new construction additions to the building.

A project at 7336 N Greenwich Ave has been submitted for building permit review by Studio 3 Architecture:

New 3 story, 18 units multifamily apartment building with associated site works. Trash enclosure attached to building.

A project at 1336 E Burnside St has been submitted for building permit review by Urban Development Group:

Projectdox – construct new 5 story 140 unit mixed use building with parking garage in basement; associated site work

Metro Reports: PDX PACR, Old Fire Station Property, 8130 SE Woodward, and more

The $268 million PDX Parking Additions and Consolidated Rental Car Facility will include 2,225 long-term parking stalls and 2,071 stalls for rental cars.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers April 22nd to April 28th, 2019.

Early Assistance has been requested by WDC Properties for a project at 1604 SE Cesar E Chavez Blvd:

Remove duplex and construct new 50 unit apartment complex with IH for bonus.

Early Assistance has been requested by Carleton Hart Architects for a project at 1535 NE 17th Ave:

Proposed mixed use project adjacent to existing (to remain) church. Proposed development includes 6-story, 96 unit affordable housing, over 24,000sq ft office, church and classroom spaces. Street vacation requested.

Early Assistance has been requested by Allusa Architecture for a project at 422 NE Beech St:

New 8 unit hotel, hotel amenities include an exercise room/workspace on the ground floor. A separate ground floor office space is also provided.

Early Assistance has been requested by Quilici Architecture and Design for a project East of 6140 SW Boundary St:

Develop the property in phases as affordable rental housing and expansion facilities for Cedar Sinai Park, the non-profit senior living and care organization that owns the property.

A Pre-Application Conference has been scheduled by Abbasi Design Works for a renovation of the Old Fire Station Property at 510 NW 3rd Ave:

Restoration and small addition (of 1600 sq ft) to existing URM building, Engine House #2. Stormwater management to be managed using flow-through planters and water quality treatment.

A project at 2510 NE Sandy Blvd has been submitted for a Type II Adjustment Review:

5-story (with mezzanine) mixed-use building. Adjustment to Building Facades Facing Sandy Blvd standard (33.575.110).

Buildings permit are under review for the PDX Parking Additions and Consolidated Rental Car Facility:

New 4 story airport operations office with rental car retail on the ground floor of the building, offices on floors 2-4, with associated site improvements related to the adjoining new 6 story PACR parking garage.

New 6 story parking garage with associated site improvements, exit helix ramp revisions, elevated roadway and bridge connections to existing P1/P2 and QTA buildings serviing Rental Car and Long Term parking.

A building permit was issued to Koble Creative Architecture for a project at 4647 SE 40th Ave:

New 15 unit apartment building comprised of a two-story wing and a three-story wing with a connecting bridge; onsite stormwater

A building permit was issued to Mentrum Architecture for a project at 1834 NW 25th Ave:

Construct new 5 story 25 unit apartment building with no parking – see folder comments

A building permit was issued to Fosler Portland Architecture for a project at 8130 SE Woodward St:

Construct new 3 story 19 unit apartment building; no parking; site work included; interior trash enclosure (sep mt)

Metro Reports: 72Foster, SW 3rd & Ash, Powell Blvd Target, and more

The former AMF Bowling Alley on Powell is being converted into a Target

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers September 25th to October 1st, 2017.

Early Assistance has been requested by CE John for a project at 1715 NE 33rd Ave:

Current Code – New Multi-Tenant retail building with surface and rooftop parking.

Early Assistance has been requested by Koble Creative Architecture for a project at NE 42nd & Prescott:

Construction of new 4-story apartment building (19 units), with ground floor retail and parking.

A project at 4708 NE Sandy Blvd has been submitted for Type II Design Review by Koz Development:

New construction of mixed use building with 114 residential apartments over commercial space. One modification to bike parking.

A structural permit has been submitted for review by GBD Architects for SW 3rd & Ash:

STR 01 – Partial permit for excavation, shoring, foundation, structural shell and all under slab and perimeter utility for the project. One level below parking with 6 stories above grade

A building permit was issued to MAJ Development for the Powell Blvd Target at 3031 SE Powell Blvd:

Change of use and occupancy at shell from A-3/S-2 to M/S-2; addition of warehouse storage, loading area and trash enclosure; no current interior occupancy without T.I.; return to shell; remove all interior walls and fixtures; replace front storefront; new interior walls to separate space; remodel garage seismic upgrade is only at the garage level, and at the first floor. 10% increase on seismic load. Upper structure and roof is not upgraded . Amit coordinated in the early stage the sismic requirements with babrak amiri and with the applicant

A building permit was issued to Otak Architects for a project at 1823 SE 50th Ave:

New 4 story, 19 unit apartment building, includes associated sitework ***separate mechanical permit required***

A building permit was issued to Holst Architecture for 72Foster at 5005 SE 72nd Ave:

New four-story mixed-use multi-family building with 101 apartment units over ground floor retail and residential services; 35 on-site parking stalls Septic Decommissioning Required. Call for Inspection 842.

Metro Reports: 4130 SE Division, 4905 N Interstate, 1714 NE 45th, and more

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Early Assistance has been requested by Baysinger Partners for a project at 4130 SE Division St:

Review is for current code. Construction of a 4 story, 19-unit residential, multifamily building

Early Assistance has been requested for a project at 2701 NE 102nd Ave:

Current code. Construct (2) 4 unit apartments buildings on site with existing single family residence. Shared kitchen, living space, and bathrooms.

Early Assistance has been requested by Carleton Hart Architecture for a project at 6324 NE 42nd Ave:

New affordable housing apartment building. 59 units. New code

Early Assistance has been requested by Koble Creative Architecture for a project at 4242 SE Milwaukie Ave:

New Zoning Code – Proposal for a new mixed use, 4 story, multi family building approximately 37 units.

A Type II Adjustment Review has been submitted for a project at NW 24th & Raleigh:

New 3-story condominium in need of adjustments: building setbacks (33.120.220.D) and building coverage and pedestrian standards (33.120.225). Please note that the building permit will be applied for next week.

A project at 4905 N Interstate Ave has been submitted for building permit review:

New 3-story, 12-unit apartment complex***fire sprinkler systems, fire alarm, mechanical, plumbing, electrical separate permits***

A project at 6234 N Montana Ave has been submitted for building permit review by CIDA Architects:

New 3 story, 19 unit apartment building w/ bike storage & trash room on first floor; includes associated sitework *** w/ 17-203579-mt ***

A new building permit application has been submitted for a project at 316 NE 28th Ave, replacing an earlier permit:

Construct new 4-story, 119 unit mixed use-apartment building with basement level; 1st level 3 retail tenant spaces, trash loading area, and lobby

A building permit was issued to Deca Architecture, Inc for a project at 1714 NE 45th Ave:

New 3 story apartment building with basement (8 units) and associated site work; includes retaining wall; trash room inside

Hoodworks Approved by Design Commission (images)

The Design Commission has approved a Hoodworks, a proposed office building in South Portland. The four story building by Koble Creative Architecture for Summit Development Group and Point B Development will be framed out of Cross-Laminated Timber. The 16,900 sq ft buiding will include retail/office space at the ground floor. 9 vehicular parking spaces and 7 bike parking spaces will be provided in a tuck-under parking area.

Hoodworks

Read More

Metro Reports: Jasmine Block, 1645 SE Nehalem, 6847 N Interstate, and more

Portland State University is planning a new 9-story building on the Jasmine Block

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Early Assistance has been requested by Allusa for a project at SE 137th & Woodward:

Proposal is to build 6-8 apartments on the property. No affordable housing. Possible street dedication.

Early Assistance has been requested by Studio 3 Architecture for a project at 5733 NE Martin Luther King Jr Blvd :

18-unit condo development (3 buildings). 13 unit site parking spaces with access from MLK Jr Blvd

Early Assistance has been requested by Tahran Architecture and Planning for a project at 5434 SE Milwaukie Ave:

New 4-story apartment building (28 units). He is proposing to use community design standards.

Early Assistance has been requested by Urban Development Group for a project at 1645 SE Nehalem St (previously 1637 SE Nehalem St):

To discuss new 4 story residential building between 58 & 65 total apartments – to be a receiving building for affordable housing – proposal would include the withdrawal of CO 17-108558

A Pre-Application Conference has been scheduled to discuss development on the Jasmine Block:

Portland State University – new construction of a 9 story academic/classroom/office building with ground floor commercial use.

A Pre-Application Conference has been scheduled by Koble Creative Architecture to discuss a project at 4619 SE 40th Ave:

Zoning Map Amendment requested to change zoning from R2 to R1. Project will include: demolition of existing duplex and construction of 15 dwelling units in connected structures with rooftop deck access & community garden with children’s play area.

A project at NE 67th & Halsey has been submitted for Type II Design Review:

New construction of a self storage building in the CG zone.

A project at 6847 N Interstate Ave has been submitted for building permit review by Doug Circosta Architect:

New 51-unit apartment building with on-site surface parking