A master plan for the redevelopment of the former Post Office site in the Pearl District has been presented to the Design Commission. Known as the Broadway Corridor, the full build-out the site will include approximately 4 million square feet of new commercial, employment, and residential development. The concepts by ZGF Architects build on the 2015 Framework Plan, which was used as part of the decision making process when the city purchased the site. Developer Continuum Partners of Denver is acting as an adviser during the master planning process.
Prosper Portland is moving forward with a second phase of development in Lents Tower Center.
The Oregonian reported that the developers of the Block 216 tower are betting on achieving record prices, with $1,350 to $1,900 per square foot condominiums units and hotel rooms at an average rate of $450 a night.
Prosper Portland is moving forward with a second phase of development in Lents Tower Center, reports the Oregonian.Blocks D & E at SE 92nd Ave will include 244 units of multifamily rental housing; the adjacent Block F will be offered to the Portland Housing Bureau for affordable housing; and the Bakery Blocks site at 5716 SE 92nd Ave will include new commercial space and a public plaza, with the retention of Zoiglhaus Brewing.
The Daily Journal of Commercewrote about developments along the MAX Orange Line*, including the under-construction Dean River Apartments at 3255 SE 17th Ave, and proposed projects at 4245 SE Milwaukie and SE 8th & Division.
Design Advice has been requested by ZGF Architects for the Portland Proper Hotel at NW 13th & Irving.
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers July 29th to August 4th 2019.
Design Advice has been requested by ZGF Architects for the Portland Proper Hotel at 1202 NW Irving St:
10-story/170,000 gsf hotel including a ground floor lobby, one floor of below grade parking, and a rooftop amenity.
Early Assistance has been requested for a project at 7918 SE Crystal Springs Blvd:
Construction of a new 150-unit multi-family development in two (2) 4-story buildings. The development will include surface parking, detached garages, outdoor play ground, and open space. Access will be from SE Harney St and SE Crystal Springs Blvd. Stormwater management will be designed to comply with local requirements for the treatment of water quality and quantity. Infiltration rates are high on-site, so detention is not anticipated as part of this project.
Early Assistance has been requested by Scott Edwards Architecture for a project at 3800 SE 164th Ave:
Three story, 71 unit mult-family building, consisting entirely of affordable housing, plus surface parking. Stormwater to be treated on site. A lot line adjustment will be needed as part of the proposal.
Early Assistance has been requested by Ankrom Moisan Architects and the Portland Housing Bureau for a project at 11332 SE Division St:
Project consists of 60 units of low barrier permanent supportive housing located at 11332 SE Division on a 1.07acre site, R1 zoning.
Early Assistance has been requested by Hacker Architects for a project at 4245 SE Milwaukie Ave:
Anticipated to be new 5-story multi-family residential building with level 1 having a partially below grade parking level at NW side of site. Total building will be 124,345 gross sf (105,317 sf FAR). 160 units plus residential amenities. Inclusionary Housing will be triggered, and provided on-site t standard rates. Stormwater treatment is anticipated on-site via interior courtyards and flow-through planters.
Early Assistance has been requested by WDC Properties for a project at NE 55th & Glisan:
New 4-story multifamily residential structure containing 22 apartment units. No parking is proposed. Stormwater will be treated on-site via drywell. Type V-A construction. Ground units to contain (1) accessible type A unit and (6) accessible type B units.
Early Assistance has been requested by The Neenan Company for a project at SE 88th & Powell:
Two-story clinic, classified as traditional office occupancy use, with entrance off Powell and from within site. 175 surface parking spaces, separated as public parking and employee parking. Staff parking entry from east side of site being negotiated with adjacent property owner. Second drive entry on 88th Avenue application being submitted to transportation.
Early Assistance has been requested by GBD Architects for a project at SE 2nd & Ash:
The proposed project is a 79,795 sf building (with less than 60,000 sf of industrial office, 5,000 sf of traditional office, ground floor retail and structured parking).
The building has a day lit basement level and first floor of concrete with 5 levels of Type 3-A heavy timber above. Stormwater will be collected on the roof of the building and treated in flow through stormwater planters on the third level.
A Pre-Application Conference has been scheduled by Guardian Real Estate to discuss a project at 131 NE Martin Luther King Jr Blvd:
Construction of an 8-story hotel and associated public improvements. Guestroom count is expected to be 168 keys. Gross building square footage is expected to be 104,330+/-. Stormwater disposal methods: it is required to provide a 100% eco-roof, with up to 40% exemptions allowed for mechanical and rooftop equipment. However, if the total provided is 70% (or more), all management can be met and direct discharge to the public systems is allowed. Proposal is targeting a minimum of 70% eco-roof.
The De Paul Treatment Center at 830 SE 102nd Ave has been submitted for a Type III Design Review by Holst Architecture:
53,150 sq ft drug and alcohol treatment center for adults. The proposal includes 94 beds for short and medium term inpatient care with associated kitchen and dining areas, as well as meeting and amenity spaces for care recipients. A portion of the building will be used to provide outpatient treatment services and administrative space for building staff. Three modifications are requested: one for maximum setback on 102nd (to be 10′) 33.150.215.C; one for the fence that are more than 50% sight obscuring may be up to 3 1/2 ft high within 10′ of street lot line (33.150.285); and one for the vehicle areas not allowed between building and street in pedestrian district (33.266 Table 266-3).
A building permit was issued to Urban Development Group for a project at 2590 NW Upshur St:
New 5 story wood framed 146 unit apartment building with associated site work
A building permit was issued to SRG Partnership for the University of Portland Joe Etzel Field at 5000 N Willamette Blvd:
New seating and amenities for Joe Etzel field to include: press box, concessions, seating and restrooms. Meeting room, associated sitework and new landscaping between Chiles Center and stadium
Design Advice has been offered for the Dairy Apartments, a development proposed on the site of the former Sunshine Dairy in Kerns. The 7-story building is being designed by Hacker Architects for developer NBP Capital. 274 residential units are proposed, with the potential for a small amount of ground floor retail. 93 vehicular parking stalls are proposed in a below grade parking garage. 303 bicycle parking spaces would be provided, with 42 proposed in bike room and remaining spaces provided in the units.
The building will be subject to the city’s inclusionary housing rules, which require the provision of affordable housing or the payment of a fee-in-lieu.
A proposed 23 story tower in the Pearl District has gone in front of the Design Commission for its first Design Review hearing. The project is being developed by Vibrant Cities in partnership with the Sunray Group, with design by Otak. The lower 11 floors of the 249′ tall building would be occupied by a 170-room Hyatt Place branded hotel. The upper 12 floors would be residential, with 110 apartment units. No vehicular parking is proposed. 174 long-term bicycle parking spaces are proposed in a mezzanine level bike room.
The building will be subject to the city’s inclusionary housing rules, which require the provision of affordable housing or the payment of a fee-in-lieu.
The Oregonian reported that one of Iceland’s top chefs will open a new restaurant, Vivian, and rooftop bar, Dóttir at the KEX Hotel.
Metro approved $22.9 million in funding for the redevelopment of Dekum Court in NE Portland. Home Forward will replace the 40 apartments currently located on the site with 160 apartments, affordable at 30% or 60% of median family income.
Two years after the completion of the Franklin High School Modernization problems are surfacing, reports OPB.
Design Advice has been offered for the Portland Housing Bureau‘s affordable housing development at 3000 SE Powell Blvd. The five story building will include 180 units, with a mix of studios, 1-, 2-, and 3-bedroom apartments. 22 vehicular parking spaces are proposed.
A building permit was issued for a 39-unit building at 5470 NE 16th Ave.
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers July 22nd to July 28th 2019.
Design Advice has been requested by Sum Design Studio for Great Scott at 701 E Burnside:
Redevelopment of existing warehouse into flex/retail retaining existing brewery operation. New 3 story building, retail with lofts above. New 4 over 2 mixed use residential tower (approx 48 units). New 2 story retail/office at corner of Burnside and 7th.
Early Assistance has been requested for a project at 1005 NE Stafford St:
Self storage
Early Assistance has been requested by EM Architecture for a project at NE 50th & Fremont:
Proposal for a three story slab-on-grade, wood framed 11 unit apartment building including outdoor courtyard with lined storm water planter, waste-recycling room and bike parking.
Early Assistance has been requested for a project at 4144 SW Canby St:
Construction of a 76-unit apartment on the R1 portion of the site, accessed from SW Canby St. Development is proposed to remain outside the environmental overlay zones.
Early Assistance has been requested by WDC Properties for a project at 5519 SE Woodstock Blvd:
Two new 3-story, multi-family, residential structures containing 42 apartment units. No parking is proposed. Stormwater will be treated on-site via drywell. Type V-B construction. Ground units to contain one (1) accessible type A unit and 13 accessible type B units.
A Pre-Application Conference has been scheduled by Alamo Manhattan to discuss The Landing at Macadam:
Project including four separate mixed-use multifamily structures with approximately 1,200 multifamily units, ground floor retail and parking uses. Blocks 41 & 44 (along the river) will be high rises and Blocks 42 & 45 (along Bond) will be mid-rises. The project will also include greenway improvements and infrastructure.
The De La Salle North Catholic High School at 4317 NE Emerson St has been submitted for a Type III Conditional Use Review:
Type III Conditional Use to reduce the size of the existing St. Charles Church Conditonal Use site to add a De La salle North Catholic High school to the site. 4 adjustments (reduce the buffering requirement, Increase the building coverae, Increase the FAR and reduce the amount of overall landscaping)
A building permit was issued to Works Progress Architecture for a project at 5470 NE 16th Ave (previously 1616 NE Killingsworth St):
New 4 story mixed use building; retail first floor; 39 residential units on floors 2-4; interior trash enclosure; associated site work; tenant improvement to be applied separately
New 5 story mixed use building with 86 total apartment units; ground floor to include, lobby, parking garage, bike parking, trash room, 7 apartments on south elevation, and retail shell at SE corner. Site work including transformer vault. ***mechanical permit separate***
A building permit was issued for a project at 16061 SE Division St:
New 3 story self storage building with office and accessible bathroom on the main floor with associated site work***demo permits to be applied for separately***
A single-asset Opportunity Zone fund will be used to finance the Eleven West tower and the PAE Living Building. The 24 story Eleven West tower was approved in 2017, but has yet to break ground.
Building permits were issued for the NW 28th & Thurman Townhomes, which will include 8 units in four buildings.
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers July 15th to July 21st 2019.
Early Assistance has been requested by MWA Architects for a project at 12529 SE Powell Blvd:
New construction of approximately 160-180 affordable, multi-family apartments ranging in size between one bedroom and three bedroom. Development will include resident community room and support spaces along with site utilities, waste/recycling, auto parking, bike parking and play area.
A project at 3802 NE Martin Luther King Jr Blvd has been submitted for a Type II Design Review by William Kaven Architecture:
The proposed project is one of four buildings to be developed sequentially on four adjacent but separate lots that extend from the southeast corner of NE Martin Luther King Jr Boulevard and NE Failing Street south toward NE Beech Street. Modification to ground floor window and frontage standards for dwelling units. Modification for vertically hung bike rack spacing.
Building permits were issued to Fieldwork Design & Architecture for the NW 28th & Thurman Townhomes:
New 4 story 2 unit apartment building- with landscaping and site utilities
New 4 story 2 unit apartment building with landscaping and site utilities
New 4 story 2 unit apartment building – with landscaping and site utilities
New 4 story 2 unit apartment building with landscaping and site utilities
Building permits were issued for a project with two buildings at 8912 and 8922 N Kellogg St (previously 7433 N Chicago):
New three story 11 unit apartment building with shared cortyard (see 19115675CO)
New 12 unit three story apartment building with shared courtyard (see 19-115696-CO), includes associated sitework