Metro Reports: Centennial Place, De La Salle North Catholic High School, Bybee Lakes Hope Center, and more

Cascadia Behavioral Healthcare’s Centennial Place Apartments will include 15 studios, 32 one-bedroom, and 24 two-bedroom affordable apartments.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers July 13th, 2020 to July 19th, 2020.

Early Assistance has been requested for a project at 4624 SW Dickinson St

Partial redevelopment of existing apartment complex. Remove 2 existing apartment buildings from the site and add 2 new buildings and a total of 300 dwelling units on site. Stormwater disposal methods to be determined.

Early Assistance has been requested by Polyphon Architecture & Design for a project at 1213 N Ainsworth St

Proposed new development consisting of two four-story congregate living structures and trash enclosure. Stormwater to be infiltrated on-site via drywell within the central courtyard.

Early Assistance has been requested by Brett Schulz Architect for a project at 5035 NE 42nd Ave

New five story assisted living facility for developmentally disadvantaged individuals, some of whom drive. The ground floor contains a small parking area, pharmacy and building lobby. Floors 2 thru 4 contains a total of 24 group living sleeping rooms with shared dining room and commercial kitchen. The fifth floor contains offices for the operator and staff of the facility.

A building permit has been submitted to Otak Inc to convert the never occupied Wapato Corrections Facility at 14355 N Bybee Lake Ct into the Bybee Lakes Hope Center:

BYBEE LAKES HOPE CENTER/SHELTER – tenant improvement to existing building to create a re-entry program for the houseless

A building permit is under review for Centennial Place at 3800 SE 164th Ave:

CENTENNIAL PLACE – Three story, 71 unit multi-family building, consisting entirely of affordable housing, plus surface parking; includes associated site work *** w/ 20-135564-MT ***

A series of building permits were issued to Bora Architects for the new De La Salle North Catholic High School at 5310 NE 42nd Ave:

DE LA SALLE H.S. – Renovation of existing building for new high school, including seismic upgrade, new finishes, mechanical, electrical, and fire protection *** w/19-256420-CO, 20-106062-CO, 19-256433-MT, & 20-106063-MT ***

DE LA SALLE H.S. – New 21,000 s.f. gym, commons, and commercial kitchen for new high school; new driveway, parking, and associated site work *** w/20-105975-CO, 20-106062-CO, 19-256433-MT, & 20-106063-MT ***

DE LA SALLE H.S. – New 732 s.f. structurally independent covered walkway between the new and existing buildings *** w/19-256420-CO, 20-105975-CO, 19-256433-MT, & 20-106063-MT ***

Building permits were issued to Edge Development for a project at 5635 and 5645 NE Glisan St (previously 5625 NE Glisan St):

New 3 story, 12 unit apartment building with trash room, electrical room, and associated site work and covered bike storage area . W/19-218545 MT

New 3 story, 13 unit apartment building with associated site work and covered bike storage area

A building permit was issued for a project at 5321 NE Glisan St (previously 5315 NE Glisan St):

New single story building for use a convenience store; site work to include new walkway, landscaping, and 100sf detached trash enclosure; ***Mechanical permit separate*** w/19-261541-rs septic decommissioning required. Call for inspection 842.

Metro Reports: 3720 N Vancouver, Live Nation South Waterfront, VC Fargo, and more

A building permit was issued to Fieldwork Design & Architecture for a four story heavy timber office building at 3720 N Vancouver Ave.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers August 26th to September 1st 2019.

Design Advice has been requested by Hacker for the Live Nation South Waterfront venue:

Proposed interim artist amphitheater including public bathrooms, terraced bleacher seating, performance stage, pedestrian walkways, concession stands, local brewery tap-house and artist back stage venue. Utilities will be installed to all on-site structures. Life of lease 7 years with extensions.

Early Assistance has been requested by Brett Schulz Architect for a project at 308 NE Dekum St:

New construction of a 4-level apartment buiding with (13) 1-bed units and (27) studio units on an approximately 100’x72′ lot. Proposed stormwater disposal method will be drywells under the courtyard. The applicant intends to meet community design standards.

Early Assistance has been requested for a project at 208 SE 148th Ave:

Multi-family development with approximately 150 dwellings units. Proposed stormwater disposal methods not yet identified.

A Pre-Application Conference has been scheduled to discuss a project at 2610 SE Hawthorne Blvd:

A Pre-Application Conference to discuss options for additional development on the site of Holman’s Funeral Home. The site and buildings are designated as a Historic Landmark. There are two options proposed: relocating the building to another portion of the site and then developing the rest of the site or leaving the building where it is and developing around it. The applicant would like to discuss the possibility of a Zoning Map Amendment from the existing zoning (CM1 and CM2) to CM3. These are all Mixed Commercial zones that allow both commercial and residential development.

A Pre-Application Conference has been scheduled to discuss a project at 9919 NE Glisan St:

A Pre-Application Conference to discuss an 8-story apartment building with 98-162 residential units. The height of the building is 89 feet. The building footprint is 9,969 square feet. The ground floor will include a lobby, bicycle storage, a 1,000 square foot commercial tenant space, mechnical rooms, trash room, elevator, stair towers and residential units. The eighth floor will include a roof deck. No off street parking or loading space is proposed.

A project at 2326 N Vancouver Ave has been submitted for building permit review by Fosler Portland Architecture:

New mixed use apartment with 19 units, with shell retail tenant space, trash room, bike room, community space and one apartment on ground floor, six units each on floors 2-4 ***mechanical separate***

The VC Fargo at 25 N Fargo St has been submitted for building permit review by Jackson Main Architecture:

New seven story, mixed-use building, apartments on upper 4 levels, groudn level includes commercial, parking garage (car stacker), storage, and common ares. ***mechanical to be separate***

A project at 7336 N Greenwich Ave has been submitted for building permit review:

New 3 story – 16 units apartment building with associated site works. Trash enclosre inside. Demo for existing house to be pulled separately.

A project with two buildings at 5625 NE Glisan St has been submitted for building permit review:

New 3 story, 12 unit apartment building with associated site work and covered bike storage area

New 3 story, 13 unit apartment building with associated site work and covered bike storage area

A building permit was issued to Holst Architecture for Halsey 106 at 10550 NE Halsey St:

6-story, mixed-use development fronting NE Halsey St and the existing Gateway Discovery Park consisting of 40 units of affordable housing and 35 units of market ratehousing.

A building permit was issued for a project at 6263 N Cecelia St:

New construction of 4 story, 21 unit apartment building 20,083sf, interior trash room, DFS for fire sprinklers and bolt on balcony with integrated guardrail

A building permit was issued to Fieldwork Design & Architecture for a project at 3720 N Vancouver Ave (previously 121 N Beech St):

New 4 story mixed use building; shell only with ground floor retail; associated site work ***mechanical to be obtained separately***

Metro Reports: PAE Living Building, Pepsi Blocks Phase 1A, LISAH, and more

PAE Living Building
The PAE Living Building at SW 1st and Pine was recently approved by the Historic Landmarks Commission, and has now been submitted for building permit review.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers June 24th to June 30th, 2019.

Design Advice has been requested by Hacker for a project at 2865 SE Division St:

10-unit (approx 37,000 sf) multi-family project with a ground floor restaurant tenant space and 20 parking spaces (with access from SE 28th). Outdoor space is provided in individual terraces and a common roofdeck.

Early Assistance has been requested for a project at 1726 NE 82nd Ave:

Proposal is for a 77 unit apartment with retail on the ground floor.

Early Assistance has been requested for a project at 5625 NE Glisan St:

Demo existing residential building. Consolidate adjacent lots through the County. Construct 2 new apartment structures on a single lot, 2 building permits. Stormwater to be treated in underground detention in the common courtyard or rear setback.

The Pepsi Blocks Phase 1A at 2505 NE Pacific St has been submitted for a Type III Design Review by Mithun:

Phase 1A of the Planned Development for redeveloping the Pepsi Bottling Plant on NE Sandy Blvd. Includes the renovation of the existing mid-century Pepsi warehouse, one new mixed-income apartment building (218 units proposed), below-grade parking, a new publicly-accessible Plaza, and design of a multi-modal east-west connector (NE Pacific Street Woonerf). Modifications are requested to 33.130242.C: Transit Street Main Entrance and 33.266.200.C: Long Term Bicycle Parking Space Dimensions. Adjustment requested to 33.266.310: Loading Standards

The 1500 SW Taylor Apartments have been submitted for building permit review by Leeb Architects:

Review w/ 19-178918-MT New construction 7-story apartment building. 5-story Type IIIA residential building over a 2-story Type 1A podium. The building contains 105 residential units and amenity spaces. The Podium level structure has parking for 19 cars, 2 loading spaces 71 bicycle parking spaces, a leasing office, a small retail tenant shell space and apartments.

A project at 3240 N Williams Ave has been submitted for building permit review:

New wood frame 4 story mixed use building with associted siteworks. 12 residential units over ground floor. Retail, trash, parking, electrical room and lobby on ground floor. Separate demo 18-177160-co.

A project at 904 SE Division St has been submitted for building permit review by LRS Architects:

New Response/Service Center Facility for NW Natural consisting of a fire-sprinklered 3-story office building and an attached 2-story storage building. Includes reconfiguration of parking and associated site work *** DFS for pre-fabricated metal building *** w/19-186013-MT ***

The PAE Living Building at SW 1st and Pine has been submitted for building permit review by ZGF Architects:

Review w/ 19-158248-MT New construction of 53,646 GSF, 5-story office building in historic district. Project is utilizing elements such as cross laminated timber (CLT), composting toilets, and water filtration/reuse to achieve the Living Building Challenge (LBC) certification. Will house PAE’s Porltand office and other tenants. Includes retal spaces at the ground floor.

Building permits were issued to Holst Architecture for LISAH (Low Income Single Adult Housing) at 8550-8580 N Argyle Way:

Pre fab congregate living facility consisting of 2 floors with 6 type B sleeping units, 1 kitchen and 2 bathrooms per floor.

Pre fab congregate living facility consisting of 2 floors with 6 type B sleeping units, 1 kitchen and 2 bathrooms per floor.

Pre fab congregate living facility consisting of 2 floors with 6 type B sleeping units, 1 kitchen and 2 bathrooms per floor.

New three story, (bld #1) multi-family, prefab building consisting of 35 studio units, 1 one bedroom unit, 2 offices, kitchen/community room, pantry, laundry room, 2 utility rooms, and elevator.

Building permits were issued to CIDA Architects for a project at 7676 and 7686 N Lombard St:

New 3 story (12) unit apartment building

New 3 story (12) unit apartment building with detached 54 sf trash enclosure and associated site work